Bexar County / San Antonio /

Omicron Drive campus (SAT5, SAT6)

Operating · oversight onlyCyrusOne · Record updated 2026-11-27

Draft record. This page has not yet been checked line by line against the source documents. Treat it as a lead, not a citation.

Two two-story CyrusOne data centers on 22 acres at Texas Research Park, outside the San Antonio city limits. State filings estimated completion of the first building (SAT5) in July 2020 and of the first two data halls in the second (SAT6) in January 2025; the tracker Baxtel gives 2020 and January 2025, and the San Antonio Report described two operating facilities on the campus in October 2026. CyrusOne lists 33 MW of IT capacity for the two buildings. The appraisal district shows the neighboring 9.96-acre lot at 14785 Omicron Dr passed from a CyrusOne entity to the City of San Antonio by deed dated 15 January 2026; state stormwater records and the San Antonio Report describe a substation there. A tracker, Baxtel, says the lot was once planned for a third building, SAT7, that was cancelled before construction; no record opened confirms that plan or a cancellation. The state lists one air quality complaint, about smoke, for the regulated entity covering this campus and SAT8/SAT9: received in July 2025 and closed that September after a compliance investigation, with no notice of violation or enforcement issued and no findings published.

Where this stands and what you can do

The site is built and running. The options now are oversight: reporting problems, asking that the terms of its agreements be enforced, and weighing in when it asks to expand or renew a permit.

  1. Report noise, odor or smoke. Generator testing and on-site power are regulated by the state environmental agency. Complaints are logged and investigated.

    Contact: TCEQ: comment on a pending permit · TCEQ: environmental complaint

  2. Ask how the agreements are being enforced. If the site has a tax abatement or a utility agreement, ask for the annual compliance reports.

    Contact: San Antonio City Council · how to speak or comment

    A letter you can copy: ask how the agreements are being enforced

    Send to: City administrator or county judge, with a copy to your council member or commissioner. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Omicron Drive campus (SAT5, SAT6) - compliance with its agreements
    
    Dear [Name],
    
    I live near Omicron Drive campus (SAT5, SAT6) (CyrusOne). The project has agreements with [the city / the county] that carry conditions. I would like to know how they are being checked. Please tell me:
    
    1. Which agreements are in force (tax abatement, development agreement, utility service, road use), and where the signed copies can be read.
    2. What the company must report each year, and whether those reports have been received.
    3. Who on staff is responsible for checking compliance, and what happens if a term is missed.
    4. How a resident should report a problem at the site (noise, dust, traffic, water), and to whom.
    
    If this is easier to answer as a public information request, please treat it as one under Government Code chapter 552.
    
    Thank you,
    [Name]
    [Address]
  3. Watch for expansions. New buildings, more generators and more water each need new permits or votes.

    Contact: Bexar County Commissioners Court

    A letter you can copy: write to the commissioners court

    Send to: County judge and commissioners. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center development in Bexar County - Omicron Drive campus (SAT5, SAT6)
    
    Dear Judge and Commissioners,
    
    I live in Bexar County near Omicron Drive campus (SAT5, SAT6) (CyrusOne).
    
    I understand the county's power over land use outside city limits is limited. I am asking you to use the authority you do have:
    
    1. Grant no tax abatement or other incentive without a public hearing, published terms, and a clawback.
    2. Use the court's control over county roads to make sure the builder, not county taxpayers, pays for damage from construction traffic.
    3. Apply the county's subdivision, drainage and fire code rules in full, and say publicly which apply to this site.
    4. Post every agreement with a data center developer on the county website.
    5. Ask our state legislators for the authority counties need to set reasonable standards for projects of this size.
    
    Please let me know when the court will next take up an item involving this project.
    
    Thank you,
    [Name]
    [Address]
  4. Ask for the documents. Water use, permits and agreements are public records, though some utilities resist releasing them.

    Contact: How to file a public information request

  5. Ask the state for reporting rules. Whether a data center must disclose its water and power use is a question for the Legislature.

    Contact: Who Represents Me (Texas Legislature) · Office of the Texas Governor

    A letter you can copy: write to your state senator and representative

    Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center siting and reporting standards - Bexar County
    
    Dear [Senator / Representative] [Name],
    
    I am your constituent in Bexar County, where Omicron Drive campus (SAT5, SAT6) (CyrusOne) is [proposed / being built / operating] near homes.
    
    I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
    
    1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
    2. Require data centers above a set size to report their water and electricity use each year, publicly.
    3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
    4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
    
    Please tell me your position on these, and whether a bill addressing them is filed or planned.
    
    Thank you,
    [Name]
    [Address - so your office can confirm I am a constituent]

This is general information about how local and state decisions get made, not legal advice.Who decides what, and every contact and letter in one place.

Legal entities
C1 San Antonio V TRP LLC; CyrusOne LLC
Also known as
CyrusOne San Antonio SAT5-SAT6; CyrusOne SAT TRP1; CyrusOne SAT V; CyrusOne SAT VI - TRP 2; Cyrusone - SAT TRP USAA; SAT7 (third building in a tracker listing; not confirmed in any record); CyrusOne Substation; C1 SAT X Replat
Location
14719 Omicron Dr, Texas Research Park (early state filings give Zeta Drive and Theta Drive)
Jurisdiction
Outside the San Antonio city limits, in the city's extraterritorial jurisdiction in unincorporated Bexar County. The appraisal district lists Bexar County, Northside ISD and Bexar County Emergency Services District 2 among the taxing units, and not the City of San Antonio. A 2023 city plat memo for a neighboring tract says zoning does not apply outside the city limits.
Site
22.04 acres
Power
33 MW
Investment
State building registrations list $64 million for the first building (2019), $15 million for its second-floor fit-out (2020), $50 million for the second building (2021) and $32.25 million for that building's first data halls (2024) (TDLR). CyrusOne's chief executive cited about $1 billion of capital investment in San Antonio to date in the company's release on the groundbreaking next door. The appraisal district's 2026 value is $129,200,000.
Water
CyrusOne's page for SAT5-SAT6 says "Water-Free Cooling" with "minimal water usage for humidification and maintenance" (company website, read November 2026). On a September 2026 press tour the operations director described a closed-loop cooling system (San Antonio Report, 2026-10-02).

Documents and sources

34 items: Government records (24) · Appraisal district records (2) · News and company statements (8)

Government records

Ordinances, resolutions, agreements, notices, permits and filings.

DateDocumentFromLink
2026-03-12PUC Docket 58276 filings list: CPS Energy Omicron 138 kV transmission line
Application filed 2025-06-27, proposal for decision 2025-12-05, Commission order 2026-03-12. Intervenors are individuals and landowner entities; CyrusOne, QTS and CloudHQ do not appear among the filers.
Public Utility Commission of TexasOpen
2025-09-02TDLR project TABS2026000039: Cyrus One - SATV - San Antonio
Office tenant improvement, 1,900 square feet. $1,000,000; December 2025 to March 2026. Owner C1 San Antonio V TRP LLC.
Texas Department of Licensing and RegulationOpen
2025-07-21TCEQ complaint 443715: complaint status page
Received 2025-07-21 from one complainant; nature smoke; program air quality; regulated entity RN110927639 (SAT5 SAT6 SAT8 SAT9), 14719 Omicron Dr. Investigation 2091576 dated 2025-08-29. Status closed 2025-09-04. "No NOV/NOE has been issued." The page says more information will be available on approval of the investigation report; the report itself was not obtained.
Texas Commission on Environmental QualityOpen
2025-06-27Application to amend a certificate of convenience and necessity, Omicron 138 kV transmission line
Places the Omicron Substation about 0.35 miles west of Potranco Road (FM 1957) and State Highway 211. Estimated cost $40,042,000 to $64,832,000 depending on route; construction January to November 2027. That description is consistent with the City-owned lot at 14785 Omicron Dr next to this campus, but the application names neither the parcel nor CyrusOne; the match is an inference.
CPS EnergyOpen
2025-06-27Attachment 3 (Need), including the ERCOT Independent Review of the CPS Energy Omicron Reliability Project
ERCOT's review says CPS Energy submitted the project in February 2024 to address violations "due to new load at the Omicron substation"; CPS's estimate then was $42.5 million with a June 1, 2027 in-service date. Customers are not named.
CPS Energy / ERCOTOpen
2024-09-16TCEQ RN112046800, Cyrus One SAT VI-Install: construction stormwater permit TXR1538SD
Held by CPS Energy from 2024-09-16; active. Southwest of Zeta Drive and Potranco Road. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
2024-08-29TCEQ RN110927639, SAT5 SAT6 SAT8 SAT9, 14719 Omicron Dr: air registrations 159643 and 177392, storage tank and stormwater permits
Owner and operator CyrusOne LLC. Air new source registrations 159643 (initial 2020-01-07; revisions 2020-09-10, 2023-05-01, 2023-07-21, 2024-06-25 and 2024-07-23) and 177392 (2024-08-29), both active; petroleum storage tank registration 91156; construction stormwater permits TXR1538HC (Whiting-Turner, 2021, cancelled) and TXR1514JV (Rogers-O'Brien, 2022, expired). Lists air quality complaint 443715 (smoke, one complainant), received 2025-07-21 and closed 2025-09-04, and a compliance investigation dated 2025-08-29; TCEQ's complaint page says no notice of violation or enforcement was issued and publishes no findings. No enforcement orders are listed. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
2024-06-10CPS Omicron Reliability Project, ERCOT Independent Review status update to the Regional Planning Group
Link from a search result; not opened. The independent review itself is reproduced in Attachment 3 of the CPS Energy application.
ERCOTOpen
2024-03-18TDLR project TABS2024014061: CyrusOne SAT VI - DH 130 & 230 N Fitout
Tenant improvements of data halls 130 and 230 (67,812 sq ft) with modular UPS systems, diesel engine generators and rooftop mechanical systems. $32,250,000; 2024-05-17 to 2025-01-31. Owner CyrusOne LLC.
Texas Department of Licensing and RegulationOpen
2023-04-25TDLR project TABS2023017499: CyrusOne - SATV - 1.5MW Load Adder
Two equipment lineups in the equipment yard and two rooftop chillers. $4,457,954; May to August 2023.
Texas Department of Licensing and RegulationOpen
2023-04-24TCEQ RN111724266, CyrusOne Substation: construction stormwater permits
North of the CyrusOne site on Omicron Drive. TXR1553MO (Rogers-O'Brien Construction, 2023-04-24, active), TXR1538PS (City Public Service Board, 2024-01-29, active) and TXR1541QD (Allbrite Constructors of Texas, 2024-03-05, cancelled). If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
2022-07-07TCEQ RN111531547, CyrusOne SAT VI - TRP 2: construction stormwater permit TXR1520JT
Held by Rogers-O'Brien Construction Company from 2022-07-07; cancelled. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
2021-04-29TDLR project TABS2021014441: CyrusOne-SAT VI TRP 2
New two-story data center (132,070 sq ft) and office (19,895 sq ft), 14719 Omicron Dr. $50,000,000; 2021-07-01 to 2022-04-30.
Texas Department of Licensing and RegulationOpen
2020-10-05TDLR project TABS2021001976: Cyrusone SAT V-Level 02 Fit-out
Upfit of level 2 shell space at SAT V TRP1, 14719 Omicron Dr: 48,000 square feet of data center space and 2,700 of office. $15,000,000. Closed.
Texas Department of Licensing and RegulationOpen
2020-01-28TCEQ RN110944675, Cyrus One - Omnicron Drive: construction stormwater permit TXR1570BG
Held by CPS Energy from 2020-01-28; cancelled. Northeast of Omicron Drive and Theta Drive. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
2019-09-05TDLR project TABS2020000302: Cyrusone - SAT TRP USAA
New two-story data center and office, 206,310 square feet, Zeta Drive. $64,000,000; 2019-09-01 to 2020-07-01. Owner Cyrusone; design firm Corgan Associates; no tenant assigned. Closed. USAA appears only in the project name.
Texas Department of Licensing and RegulationOpen
2019-09-03TCEQ RN110844891, CyrusOne SAT TRP1: construction stormwater permit TXR15982Z
Held by Rogers-O'Brien Construction Company from 2019-09-03; expired. West side of Theta Drive. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
2019-08-26TCEQ RN110843455, Cyrus One TRP, Theta Dr and Omicron Dr: petroleum storage tank registration 90776
Operator Ranger Excavating LP from 2019-08-26; owner Hays City Corporation. Listed active. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
Omicron New 138kV Transmission Line Project page
A five-mile 138 kV line to a new Omicron Substation in far west Bexar County, needed for "increasing customer load growth in the area, including new large customer loads." No customer is named. ERCOT endorsed the project 2024-07-26; the Public Utility Commission selected Route 26 on 2026-03-12.
CPS EnergyOpen
Omicron Transmission Loop Project page
CPS Energy proposes replacing the existing single-circuit 138 kV line between its Omicron Station and Rafter Station, about 1.5 miles.
CPS EnergyOpen
Qualifying data center and large data center lists
Checked November 2026: no entry for SAT5, SAT6 or any CyrusOne site at Texas Research Park.
Texas ComptrollerOpen
Chapter 312 abatement agreement registry (statewide data file)
Checked November 2026: no Bexar County or City of San Antonio agreement for this site. The only Bexar entry naming CyrusOne is the City's 2013 agreement, which expired in 2020 (see the Westover Hills SAT2-SAT4 record).
Texas ComptrollerOpen
Subdivision plats "CYRUSONE" (CB 4349A, Block 1) and "C1 SAT X Replat"
Not yet obtained. The plat names come from the appraisal district's legal descriptions. No Planning Commission item for either was found in the city's legislation file (2014 to 2021, by title) or its Planning Commission agendas (2021 to November 2026); they may have been approved administratively.
City of San Antonio / Bexar County ClerkNot yet archived. Have it?
Bexar County parcel map service (owner and address query)
Queried by owner name and street to find the property IDs listed in this record.
Bexar CountyOpen

Appraisal district records

The county appraisal district page for each parcel: owner, value, deed history.

DateDocumentFromLink
Bexar Appraisal District property 1319173
22.04 acres, CB 4349A (CYRUSONE), Block 1 Lot 3, 14719 Omicron Dr. Owner of record: C1 San Antonio V TRP LLC. Improvements of 205,476 square feet (year built 2019) and 127,832 square feet (year built 2023). Appraised value $78,000,000 (2023), $118,000,000 (2024), $130,000,000 (2025), $129,200,000 (2026).
Bexar Appraisal DistrictOpen
Bexar Appraisal District property 1416617
9.96 acres, CB 4349A (C1 SAT X Replat), Block 1 Lot 4, 14785 Omicron Dr. Owner of record: City of San Antonio. Deed history: special warranty deed dated 1/15/2026 from C1 San Antonio X LLC (document 20260009462). 2026 appraised value $1,074,951. Baxtel identifies this lot as the unbuilt SAT7 site, now the substation.
Bexar Appraisal DistrictOpen

News and company statements

Reporting and press releases. These are not public records; they are context and leads.

DateDocumentFromLink
2026-10-02Can small-group tours of data centers change hearts and minds?
Press tour of SAT5 on 2026-09-24: 22 acres, an 87,500-square-foot data center, generators with sound attenuation, rooftop chillers behind sound walls, fence-line noise testing, and a substation "the company built, then transferred to CPS Energy." Says the campus has two operating facilities and two under construction, with three more planned nearby.
San Antonio ReportRead
2026-08-17How One Data Center Company Plans to Earn Texans' Trust
CyrusOne's community affairs vice president on closed-loop cooling (about 50,000 gallons to fill, about 1,100 gallons a day) and the company's San Antonio footprint.
San Antonio Express-News via GovTechRead
2026-08-03Data centers are cropping up all over Bexar County with 23 more on the way
CyrusOne and Vantage have registered more than $1 billion of construction along Omicron Drive since 2020, per state project filings.
Texas Public Radio / San Antonio ReportRead
CyrusOne: SAT5 (tracker listing)
Construction started September 2019; opened 2020; second-floor hall fitted out 2021; capacity added 2023.
BaxtelRead
CyrusOne: SAT6 (tracker listing)
Construction started July 2021; shell complete 2023; first data halls complete January 2025; expansions through 2027.
BaxtelRead
CyrusOne: SAT7 (tracker listing)
Tracker text: "Project cancelled before construction." It says a 2020 plan showed three two-story buildings and that the lot was transferred to the City of San Antonio in January 2026 for the substation. The transfer is confirmed by the appraisal district; the SAT7 plan and its cancellation rest on this tracker alone.
BaxtelRead
CyrusOne San Antonio (Omicron) (tracker listing)CleanviewRead
San Antonio, TX: SAT5-SAT6
Company campus page: 175,000 square feet of technical space and 33 MW of IT capacity across the current development.
CyrusOneOpen

Timeline

  1. CyrusOne. Led a press tour of SAT5, described as the company's first media tour; council members Ric Galvan and Phyllis Viagran had toured earlier. Source
  2. Public Utility Commission of Texas. Approved a route (Route 26) for CPS Energy's Omicron 138 kV transmission line in Docket 58276. Source
  3. CyrusOne. C1 San Antonio X LLC conveyed the 9.96-acre lot at 14785 Omicron Dr to the City of San Antonio by special warranty deed dated 15 January 2026, per the appraisal district's deed history. The tracker Baxtel says the lot was once planned for a third building, SAT7, and was transferred for the campus substation; no record opened confirms a SAT7 plan or its cancellation. Source
  4. Texas Commission on Environmental Quality. Air quality complaint 443715 received for the regulated entity that covers SAT5, SAT6, SAT8 and SAT9: one complainant, nature recorded as smoke. TCEQ lists compliance investigation 2091576 dated 2025-08-29 and closed the complaint 2025-09-04. Its complaint page says no notice of violation or enforcement was issued; it publishes no investigation findings and does not say which building was involved. Source
  5. Texas Commission on Environmental Quality. A second air new source registration, 177392, completed for the site (named "SAT5 SAT6 SAT8 SAT9" in the registry).
  6. ERCOT. Endorsed CPS Energy's Omicron Reliability Project, a second 138 kV transmission source for the Omicron Substation. Source
  7. Texas Department of Licensing and Regulation. Fit-out of SAT VI data halls 130 and 230 registered, with added UPS systems, diesel generators and rooftop mechanical systems: $32,250,000, May 2024 to January 2025. Source
  8. Texas Department of Licensing and Regulation. "CyrusOne - SATV - 1.5MW Load Adder" registered: two equipment lineups and two rooftop chillers, $4,457,954. Source
  9. Texas Commission on Environmental Quality. First construction stormwater permit for the "CyrusOne Substation", north of the CyrusOne site on Omicron Drive (Rogers-O'Brien Construction; later permits to CPS Energy and Allbrite Constructors in 2024).
  10. Texas Department of Licensing and Regulation. "CyrusOne-SAT VI TRP 2" registered: a new two-story data center of 132,070 square feet with 19,895 square feet of office, $50,000,000, July 2021 to April 2022. Source
  11. Texas Department of Licensing and Regulation. Second-floor fit-out of SAT V registered: $15,000,000, October 2020 to March 2021. Source
  12. Texas Commission on Environmental Quality. Air new source registration 159643 for the site's emission sources completed; it was revised in 2020, 2023 and 2024.
  13. Texas Department of Licensing and Regulation. CyrusOne registered "Cyrusone - SAT TRP USAA", a new two-story data center and office of 206,310 square feet on Zeta Drive: $64,000,000, September 2019 to July 2020. The size and dates match SAT5; the record names no tenant. Source
  14. Texas Commission on Environmental Quality. Construction stormwater permit TXR15982Z issued to Rogers-O'Brien Construction for "CyrusOne SAT TRP1".
  15. Texas Commission on Environmental Quality. Petroleum storage tank registration 90776 opened for "Cyrus One TRP" at Theta Drive and Omicron Drive (operator Ranger Excavating LP).