A two-story CyrusOne data center on 10 acres at Texas Research Park, south of the company's SAT5 and SAT6 buildings and outside the San Antonio city limits. CyrusOne calls its two halves SAT8 and SAT9 and describes 276,000 square feet and 36 MW. Plans were registered with the state in November 2023, the San Antonio Planning Commission approved the one-lot plat in June 2024 and the company announced the groundbreaking that summer; the appraisal district lists two 134,388-square-foot improvements (year built 2024), the state construction filing is still open with an estimated completion of December 2025, and no tenant fit-out filing was found as of November 2026.
Where this stands and what you can do
The main local decisions have been made and building has started. It is too late to stop this phase. What remains is holding the builder to its permits and agreements, and shaping any later phase or new request.
Report problems as they happen. Dust, mud on roads, runoff, noise and night work are covered by state stormwater and air rules and by local agreements. A dated complaint to the state environmental agency creates a record that is investigated.
Ask that the agreements be enforced. Tax abatement and development agreements carry conditions and reporting duties. Ask the city or county for the compliance reports and what it is doing to check them.
A letter you can copy: ask how the agreements are being enforced
Send to: City administrator or county judge, with a copy to your council member or commissioner. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: SAT8/SAT9 - compliance with its agreements
Dear [Name],
I live near SAT8/SAT9 (CyrusOne). The project has agreements with [the city / the county] that carry conditions. I would like to know how they are being checked. Please tell me:
1. Which agreements are in force (tax abatement, development agreement, utility service, road use), and where the signed copies can be read.
2. What the company must report each year, and whether those reports have been received.
3. Who on staff is responsible for checking compliance, and what happens if a term is missed.
4. How a resident should report a problem at the site (noise, dust, traffic, water), and to whom.
If this is easier to answer as a public information request, please treat it as one under Government Code chapter 552.
Thank you,
[Name]
[Address]
Watch for the next request. Later phases, annexation, more water or sewer, and new abatements each come back for a vote. That is where terms can still be set.
A letter you can copy: write to the commissioners court
Send to: County judge and commissioners. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Data center development in Bexar County - SAT8/SAT9
Dear Judge and Commissioners,
I live in Bexar County near SAT8/SAT9 (CyrusOne).
I understand the county's power over land use outside city limits is limited. I am asking you to use the authority you do have:
1. Grant no tax abatement or other incentive without a public hearing, published terms, and a clawback.
2. Use the court's control over county roads to make sure the builder, not county taxpayers, pays for damage from construction traffic.
3. Apply the county's subdivision, drainage and fire code rules in full, and say publicly which apply to this site.
4. Post every agreement with a data center developer on the county website.
5. Ask our state legislators for the authority counties need to set reasonable standards for projects of this size.
Please let me know when the court will next take up an item involving this project.
Thank you,
[Name]
[Address]
Ask for the documents. Signed agreements, permits and inspection reports are public records.
Ask the state and federal governments for standards. Rules on siting, water reporting, on-site power and air pollution are made in Austin and Washington, not at city hall.
A letter you can copy: write to your state senator and representative
Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Data center siting and reporting standards - Bexar County
Dear [Senator / Representative] [Name],
I am your constituent in Bexar County, where SAT8/SAT9 (CyrusOne) is [proposed / being built / operating] near homes.
I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
2. Require data centers above a set size to report their water and electricity use each year, publicly.
3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
Please tell me your position on these, and whether a bill addressing them is filed or planned.
Thank you,
[Name]
[Address - so your office can confirm I am a constituent]
CyrusOne SAT 8 & 9; C1 SAT 8 & 9; CyrusOne San Antonio SAT8 Campus; CyrusOne's fifth San Antonio campus
Location
14677 Omicron Dr per the appraisal district; state filings use 14815 Omicron Drive. Texas Research Park, directly south of SAT5
Jurisdiction
Outside the San Antonio city limits, in the city's extraterritorial jurisdiction in unincorporated Bexar County. The appraisal district lists Bexar County, Northside ISD and Bexar County Emergency Services District 2 among the taxing units, and not the City of San Antonio. A 2023 city plat memo for a neighboring tract says zoning does not apply outside the city limits.
Site
10 acres
Power
36 MW
Investment
CyrusOne's state building registration lists an estimated cost of $15,000,000 (TDLR, 2023-11-10). The appraisal district valued the property at $55,733,030 for 2025 and $73,010,790 for 2026.
Ordinances, resolutions, agreements, notices, permits and filings.
Date
Document
From
Link
2026-03-12
PUC Docket 58276 filings list: CPS Energy Omicron 138 kV transmission line
Application filed 2025-06-27, proposal for decision 2025-12-05, Commission order 2026-03-12. Intervenors are individuals and landowner entities; CyrusOne, QTS and CloudHQ do not appear among the filers.
Held by DPR Construction from 2024-10-01; cancelled. Along Omicron Drive and Lambda Drive. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
TCEQ RN110927639, SAT5 SAT6 SAT8 SAT9: air registrations 159643 and 177392
The registry names the neighboring campus record for all four buildings. Air new source registration 177392 was completed 2024-08-29; whether it covers SAT8 and SAT9 generators is not stated on the page. The record lists air quality complaint 443715 (smoke, one complainant; received 2025-07-21, closed 2025-09-04) and a compliance investigation dated 2025-08-29. TCEQ's complaint page says no notice of violation or enforcement was issued, publishes no findings and does not say which of the four buildings was involved; the address on it is the SAT5/SAT6 campus. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Filing date 2024-06-03; applicant and owner C1-San Antonio VIII LLC; engineer Colliers Engineering and Design; council district "ETJ"; 10.00 acres, one non-residential lot; zoning not applicable outside the city limits; Master Development Plan 276-A, Texas Research Park, accepted 2010-04-30; no variance requested.
TCEQ RN111907937, CyrusOne SAT 8 & 9, 14815 Omicron Dr: construction stormwater permit TXR1597PX
Held by Rogers-O'Brien Construction Company LLC from 2024-02-15; cancelled. No complaints or investigations listed under this permit. If the link errors, search the RN at www15.tceq.texas.gov/crpub.
New two-story data center and office, about 279,730 gross square feet, with admin areas and four data halls, 14815 Omicron Drive. $15,000,000; 2024-04-01 to 2025-12-31. Privately funded; no tenant assigned. Status: project registered.
A five-mile 138 kV line to a new Omicron Substation in far west Bexar County, needed for "increasing customer load growth in the area, including new large customer loads." No customer is named. ERCOT endorsed the project 2024-07-26; the Public Utility Commission selected Route 26 on 2026-03-12.
The county appraisal district page for each parcel: owner, value, deed history.
Date
Document
From
Link
Bexar Appraisal District property 1441384
10.0 acres, CB 4348C (C1 SAT 8 & 9), Block 2 Lot 4, 14677 Omicron Dr. Owner of record: C1-San Antonio VIII LLC. Two computer-center improvements of 134,388 square feet each, year built 2024. Appraised value $55,733,030 (2025) and $73,010,790 (2026).
CyrusOne files to build data center in San Antonio, Texas
Not opened: the site returned a bot check. The link and summary come from a search result. The summary says county records show CyrusOne bought the land at 14815 Omicron Drive in 2021, citing the San Antonio Business Journal.
Plans filed November 2023; groundbreaking July 2024; shell enclosed by mid-2025, with generator yards on the north and south sides; no tenant fit-out filed by November 2026.
CyrusOne Breaks Ground on Fifth Data Center Campus in San Antonio
Two buildings totaling 276,000 square feet and 36 MW of IT capacity; cites about $1 billion of capital investment in San Antonio to date. The page carries a 2025-01-29 date; the groundbreaking was reported in July 2024.
San Antonio Report. Reported after a September press tour that CyrusOne's Omicron campus has two operating facilities and two under construction. Source
Texas Commission on Environmental Quality. Construction stormwater permit TXR1569SH issued to DPR Construction for "CyrusOne TRP - CPS Underground Design Assistance" along Omicron Drive and Lambda Drive; since cancelled.
CyrusOne. By this date CyrusOne had announced the groundbreaking of its fifth San Antonio campus at Texas Research Park. Its release says Bexar County Judge Peter Sakai, council members Melissa Cabello Havrda and Marina Aldrete Gavito and CPS Energy representatives attended. Source
San Antonio Planning Commission. Approved the C1 SAT 8 & 9 Subdivision plat on the consent agenda, 9-0. Staff recommended approval. Source
City of San Antonio Development Services. Plat LAND-PLAT-23-11800375, C1 SAT 8 & 9 Subdivision, filed by C1-San Antonio VIII LLC: 10.00 acres, one non-residential lot. Source
Texas Commission on Environmental Quality. Construction stormwater permit TXR1597PX issued to Rogers-O'Brien Construction for "CyrusOne SAT 8 & 9"; since cancelled.
CyrusOne. A spokesperson said the company had recently bought the property and would share its plans "in the coming months." Source
Texas Department of Licensing and Regulation. CyrusOne registered "CyrusOne SAT 8 & 9": a two-story data center and office of about 279,730 square feet with four data halls, $15,000,000, April 2024 to December 2025. Source