| 2026-10-19 | Summary: Data Center Permits Issued by TCEQ After 9/21/2026 Advocacy group's list. States that on October 13 TCEQ issued a construction stormwater permit to Sitespan, LLC for 'San Antonio Karting Complex located at 1000 Bolton Road, Marion TX.' | Public Citizen | Open |
| 2026-10-13 | TCEQ construction stormwater general permit coverage TXR1564ZS, 'SAT1' Held by Sitespan, LLC of Lenexa, Kansas (CN606572139) as operator since 10/13/2026, not by Legacy Investing. Status shown as Active on 2026-11-27. Texas Public Radio reported on October 22, 2026 that TCEQ said a permit issued October 13 to Sitespan for a Bolton Road data center project had been suspended after the governor's September 21 directive; the registry page does not show a suspension. | Texas Commission on Environmental Quality | Open |
| 2026-10-01 | Economic Development report, October 2026 Lists 'Legacy San Antonio Data Center - 1000 Bolton - (Permit issued 9.16.26)'. The report does not say which permit or whether work has begun. | City of Cibolo | Open |
| 2026-09-14 | Registered Qualifying Data Center Projects list: 'Legacy Data Center SAT-1' Checked 2026-11-27. Entry 'Legacy Data Center SAT-1', effective date 09/14/2026, with 1000 Bolton Rd Owner, LLC as owner (DC345668-OW1), occupant (DC345668-OC1) and operator (DC345668-OP1). The list has no address column; the match rests on the project and entity names. | Texas Comptroller | Open |
| 2026-09-01 | Economic Development report, September 2026 Lists 'Legacy San Antonio Data Center - 1000 Bolton Rd (Commercial Shell Building & Concrete)' in the building permit section. | City of Cibolo | Open |
| 2026-09-01 | TCEQ construction stormwater general permit coverage TXR1501ZI, Legacy San Antonio Held by Legacy Investing (CN606556132) as operator since 09/01/2026. Status shown as Active on 2026-11-27. No complaints, investigations or enforcement listed. | Texas Commission on Environmental Quality | Open |
| 2026-08-27 | Revised site plan PZ-2026-3-SP, 'Legacy San Antonio' civil construction plans, stamped and approved 47 sheets, the civil and landscape sheets by Kimley-Horn with a cover dated July 16, 2026, stamped 'Reviewed for compliance' and signed 8/27/26. Owner/developer shown as Legacy Investing, Arlington, Virginia. Site data table: Skloss Commercial Lot 1 Block 1 (Doc. 2016008606); site acreage about 38.659; one 242,640 sq ft building, 29 ft 8 in high; about 26.6 acres impervious cover; 71 parking spaces. The city's August 2026 development report gives the approval date as 8/28/2026. | City of Cibolo | Open |
| 2026-08-24 | City Engineer review letter, 1000 Bolton Road (PZ-2026-3-SP) Finds the development 'in conformance with the city of Cibolo Unified Development Code and Flood ordinances.' | Colliers Engineering & Design, as City Engineer | Open |
| 2026-08-24 | Water Use in Perspective: daily and monthly averages Follow-up table to the handout. It has no data center row. | City of Cibolo | Open |
| 2026-08-17 | Town hall handout, 'Putting Water Use Into Perspective' Graphic comparing monthly water use by land use, with a closed-loop data center shown among them. | City of Cibolo | Open |
| 2026-08-17 | Town hall presentation slides by Overwatch General presentation on how data centers operate. The city FAQ states Overwatch is not connected to any proposed project in Cibolo and was not paid. | Overwatch, posted by the City of Cibolo | Open |
| 2026-08-01 | Economic Development report, August 2026 Lists 'Revised Site Plan Approved 8/28/2026' and 'Legacy San Antonio Data Center - 1000 Bolton Rd - Commercial concrete permit issued for Building Phase 1, under plan review'. | City of Cibolo | Open |
| 2026-07-20 | City Council Ordinance Subcommittee meeting No agenda or minutes found. The July 28 staff report says the subcommittee met July 20 and recommended that council consider the approval process (by right or conditional use permit) and standards for water, energy, pollution and noise. | City of Cibolo | Not yet archived. Have it? |
| 2026-07-17 | City staff slide deck, 'Data Center Entitlements and Resources' 51 slides attached to the July 28, 2026 council item. Timeline slide: April 6 application, April 29 site plan approved, May 18 application to revise, 'No permits approved at this time.' Electric slide: the substation on Bolton Road has 100 MW capacity, 70 MW allocated to existing and proposed users and 30 MW available. Water slide: 6 acre-feet to fill the cooling system once and up to 500 gallons a day afterward; 'Package plant to be built by owner' and district sewer 'when line extended.' Read by OCR. | City of Cibolo | Open |
| 2026-07-11 | Petition to Relocate the Proposed Data Center Near I-10 and Bolton Road, Cibolo, Texas Resident petition; 4,083 signatures shown when opened on 2026-11-27. Date is the creation date shown on the page. | Change.org | Open |
| 2026-06-15 | Traffic Impact Analysis worksheet, PZ-2026-3-SP One 242.64 thousand sq ft building; 37 peak-hour trips. | Kimley-Horn | Open |
| 2026-06-01 | Economic Development report, April/May/June 2026 Adds 'Warehouse with server storage @ 1000 Bolton Rd - Commercial concrete permit in plan review'. | City of Cibolo | Open |
| 2026-04-28 | Site plan approval PZ-2026-2-SP, '1000 Bolton Rd. Site Improvements' (city-signed plan set) 17 sheets: civil and landscape sheets by Halff and three elevation sheets by GMA Architects dated February 20, 2026, whose title block reads "Legacy Investors". Owner/developer shown as 1000 Bolton Rd, LLC of San Antonio. Two buildings of 268,600 sq ft each. The city signature is dated 4/28/26 and the cover is stamped 'For site plan approval only, not released for construction.' City staff reports give the approval date as April 29, 2026. | City of Cibolo | Open |
| 2026-04-09 | GVEC electric capacity letter, 1000 Bolton Road Project States GVEC is the certificated provider, 'has adequate electric capacity to serve the project, pending construction of underground distribution facilities', and that 'binding contracts are currently in place between GVEC and project developer to guarantee capacity availability.' No megawatt figure is given in the letter. | Guadalupe Valley Electric Cooperative | Open |
| 2026-04-02 | Water Service Feasibility Study and transmittal, 1000 Bolton Road Service application received March 19, 2026; memo dated March 23; transmittal dated April 2. Request of 33 equivalent dwelling units (25 industrial, 8 irrigation), projected by the district at 13.2 acre-feet a year. Concludes the district has adequate supply through its Canyon Regional Water Authority contract. Developer cost estimated at $484,604.59. Prepared for the earlier two-building layout. The study expires six months after the transmittal unless it moves to a non-standard service agreement, which goes to the district board. The study text describes the tract as in Cibolo's ETJ; the city's records show it annexed in 2016. | Green Valley Special Utility District (study by Utility Engineering Group, PLLC) | Open |
| 2026-04-02 | Wastewater Service Feasibility Study and transmittal, 1000 Bolton Road Request of 42 industrial equivalent dwelling units; average flow about 12,600 gallons a day and peak wet-weather flow about 62,145 gallons a day at buildout. States service will not be available until the district's 1.25 MGD plant expansion is in service, that industrial pretreatment requirements apply, and that the developer extends 400 feet of 24-inch gravity main. Developer fee $310,755.48. | Green Valley Special Utility District (study by Utility Engineering Group, PLLC) | Open |
| 2026-03-01 | Economic Development report, March 2026 Lists 'Warehouse with server storage @ 1000 Bolton Rd (Site Plan Approved)'. The city FAQ says this report went to council on April 23, 2026. | City of Cibolo | Open |
| 2026-02-05 | Narrative of Application Request, Ocotillo/Marion Industrial Entitlements One page. Describes a site plan for a 39-acre property with 'two industrial buildings that will be data centers', served by Green Valley SUD for water and sewer, with a sewer main extension submitted to the district. Gives parcel ID numbers 184790 and 161667. | Halff Associates | Open |
| 2026-02-02 | Traffic Impact Analysis threshold worksheet, PZ-2026-2-SP Land use 'Data Center', 540,000 sq ft, 60 peak-hour trips against 29 for the former recreational use. | Halff | Open |
| 2025-07-08 | Ordinance 1497, rezoning of about 263 acres along IH-10 from Mixed-Use Regional Employment to Light Industrial Posted by the city with the data center material. The city FAQ states 1000 Bolton Road was not part of this rezoning. | City of Cibolo | Open |
| 2025-01-10 | Economic Development report, January 2025 (Development Projects Update) Lists 'Data Center @ 1000 Bolton Rd (Pre-Application)'. The city FAQ says council updates on the project began with the January/February 2025 report. The same line appears in each monthly report through February 2026. | City of Cibolo | Open |
| 2017-03-29 | TCEQ stormwater permit TXR15564B, San Antonio Karting Complex (expired) Held by Skloss Development, LLC since 03/29/2017 for the kart complex that preceded the data center. Expired. | Texas Commission on Environmental Quality | Open |
| 2016-08-23 | Ordinance 1173, zoning of 39.14 acres from Agricultural to Light Industrial (I-1) with a conditional use permit for a commercial go-kart complex Adopted August 23, 2016. Recites a Planning and Zoning Commission hearing on July 13, 2016 and a council hearing on July 26, 2016. The conditional use permit conditions cover the kart track's hours and lighting. | City of Cibolo | Open |
| 2016-08-09 | Ordinance 1172, voluntary annexation of about 48 acres north of Bolton Road and east of Stolte Road Passed and approved August 9, 2016. Recites public hearings on July 12 and 13, 2016. | City of Cibolo | Open |
| Planning FAQs: Data Center FAQs, Proposed Data Center at 1000 Bolton Road, and Data Center Town Hall Q&A Names Legacy Investing as developer. States a single 242,640 sq ft, 50 MW building; zoning unchanged since 2016; no public hearing was required; no city incentive of any kind; water from Green Valley SUD and electricity from GVEC; and that the project 'has met all applicable regulations and will be allowed to proceed if they decide to fund the project.' Gives water use as 'slightly more than 300,000 gallons per month.' The page gives the town hall date as August 18 in one place and August 17 in others. | City of Cibolo | Open |
| Current Development Projects: Proposed Data Center at 1000 Bolton Road Project description and the list of application documents. Lists the changes in the revised plan: two 268,600 sq ft buildings reduced to one of 242,640 sq ft; parking from 621 to 71 spaces; landscape area from 32% to 56%; 24.9 acre-feet of drainage storage. Gives building height as 27 ft 8 in; the stamped plan's site data table gives 29 ft 8 in. | City of Cibolo | Open |
| Site plan application PZ-2026-2-SP, 'Ocotillo/Marion Industrial Entitlements' Applicant Halff; property owner listed as Ocotillo Capital Partners of San Antonio. 39.15 acres, zoning I-1 with no change, two lots, proposed use Industrial. The city staff report of July 28, 2026 says the application was received April 6, 2026. | Halff, for the property owner | Open |
| Revised site plan application PZ-2026-3-SP, '1000 Bolton Road' Applicant SiTESPAN, LLC of Lenexa, Kansas; representative Kimley-Horn; property owner listed as Ocotillo Capital Partners. 39 acres, one lot, 243,217 sq ft, current use 'Vacant Go-Kart Track', proposed use 'Data Center'. Printed June 16, 2026; the city staff report says it was received May 18, 2026. | SiTESPAN, LLC and Kimley-Horn, for the property owner | Open |
| Plat of Skloss Commercial, Lot 1 Block 1 Not obtained. The stamped site plan cites the plat as Document 2016008606 in the Official Public Records of Guadalupe County; the city staff report of July 28, 2026 describes a 'Final Plat of 1000 Bolton Road (recorded in 2018)', and an image of the plat is in the staff slide deck. | Guadalupe County Clerk | Not yet archived. Have it? |
| Special warranty deed for 1000 Bolton Road Not obtained. Both site plan applications list a special warranty deed among their uploaded documents, and Polsinelli announced on June 25, 2026 that Legacy Investing had acquired the site. The seller, price and recording date were not found. | Guadalupe County Clerk | Not yet archived. Have it? |
| What's New in Cibolo: index of monthly development reports Links every monthly report from 2024 on. | City of Cibolo | Open |
| Public Notices and Completed Public Hearings pages Records the August 12, 2026 Planning and Zoning hearings on the UDC amendments for unlisted uses and for data centers, the September 8 council hearing, and their outcomes. The Public Notices page lists a December 8, 2026 council hearing on adopting the 2027 Unified Development Code. | City of Cibolo | Open |
| TCEQ Central Registry, regulated entity RN109726570 'Legacy San Antonio', 1000 Bolton Rd, Marion Checked 2026-11-27. Three stormwater permit numbers and no air authorization are listed for this site. Customers listed as operators: Skloss Development, LLC, Legacy Investing and Sitespan LLC. | Texas Commission on Environmental Quality | Open |
| Franchise tax account status, 1000 Bolton Rd Owner, LLC Delaware LLC; Texas Secretary of State registration effective 05/11/2026 (file 0806595625); registered agent Capitol Corporate Services, Inc., Austin; right to transact business Active. No officers or members are listed. | Texas Comptroller | Open |
| Franchise tax account status, 1000 Bolton Road, LLC Delaware LLC; Texas registration effective 01/30/2026 (file 0806419284); mailing address in San Antonio matching the address the site plan applications give for Ocotillo Capital Partners. The first site plan names '1000 Bolton Rd, LLC' at the same address as owner/developer. | Texas Comptroller | Open |
| Franchise tax account status, Sitespan, LLC Kansas LLC based in Lenexa, registered in Texas since 08/26/2019. Applicant on the revised site plan and holder of the October 13, 2026 stormwater coverage. | Texas Comptroller | Open |
| Green Valley SUD Agenda Center: 2026 board agendas and minutes Checked 2026-11-27. The posted 2026 board agendas (January through November) and minutes (through October 15) list non-standard service agreements by project name; none is for 1000 Bolton Road or Legacy. The October 15 minutes record a general report that the Canyon Regional Water Authority board discussed data center development. | Green Valley Special Utility District | Open |
| GVEC board and large-load records for 1000 Bolton Road Not found. The cooperative's capacity letter refers to binding contracts with the developer, which were not located. No board minutes were found online. | Guadalupe Valley Electric Cooperative | Not yet archived. Have it? |
| AgendaLink meeting portal, City of Cibolo Searched 2026-11-27. The portal's agenda item search returns no item containing the word 'moratorium', and its results for 'unlisted' show nothing after the October 19 joint workshop. The city's hearing pages show no council vote on a data center ordinance. | City of Cibolo | Open |
| Industrial development site, 1000 Bolton Road, Marion (sale listing) Broker listing of the kart track as a 39-acre development site with an 8-inch water main and half a mile of race track. | Matthews Real Estate Investment Services | Open |
| Legacy: San Antonio (tracker listing) Tracker page. Says the project has four halls and that the cooperative 'can add capacity for a second building'; these statements are the tracker's and were not found in a primary record. | Baxtel | Open |
| 1000 Bolton Road data center (Marion) (tracker listing) Tracker entry citing the City of Cibolo application. | Texas Data Center Watch | Open |
| Legacy Investing Data Center (1000 Bolton Rd, Marion) (tracker listing) Tracker page titled 'Under Construction'. The page cites no dated source for that status and says its details 'haven't yet been read back against the source.' | More Than Just Parks | Open |