HC Capital Partners
HC Capital Partners is a private investment firm developing Energy Ranch, a South Texas campus where data center tenants would build their own facilities and buy power generated on site from natural gas. It announced the project in January 2026 with Herrmann Family Companies, a San Antonio family office. State air permit filings for the site are in the names WranglerX LLC and Remuda Power LLC.
- Also known as
- HC Infrastructure Partners; Wrangler Infrastructure; WranglerX LLC; Remuda Power LLC; Energy Ranch
- Type
- Power and data center campus developer
- Headquarters
- Austin, Texas (company website); its press releases are datelined San Antonio
- Ownership
- Privately held; its releases name Herb Chambers IV as a co-founder and do not name other owners or investors. Its March 2026 release says the Energy Ranch platform is "owned and controlled by HC Capital Partners". The partner on the land is Herrmann Family Companies, described in the January 2026 release as a San Antonio-based family office with holdings in energy, ranching, farming, real estate and technology.
- Elsewhere in Texas
- Energy Ranch is its only announced project: more than 1,500 acres, a first 250 MW targeted for early 2028 and expansion to between 1 and 3 gigawatts, according to the company. The company's Energy Ranch website describes two campuses, Energy Ranch 1 and Energy Ranch 2, without locating them. Wrangler Infrastructure, described as the infrastructure platform of HC Infrastructure Partners, is to develop the power assets. No tenant or end customer has been named.
- Website
- hccappartners.com
Legal entities named in the records: HC Capital Partners; HC Infrastructure Partners; Herrmann Family Companies; Remuda Power LLC; Wrangler Infrastructure; WranglerX LLC. Search for these names, not only the company name, in agendas and appraisal records.
1 documented project
- Energy RanchProposed · decisions still open
A proposed power and data center campus of more than 1,500 acres in South Texas, announced in January 2026 by HC Capital Partners and Herrmann Family Companies. The developer targets 250 MW of on-site natural gas generation in early 2028 and 1 to 3 GW at build-out, and has not named a county. Two air registrations filed with TCEQ in November 2026 place a site named Energy Ranch in La Salle County near Cotulla, which may be a second campus; earlier public debate centered on Atascosa and Frio counties.
Sources on the company
| Date | Source | From | Link |
|---|---|---|---|
| 2026-06-26 | Evergreen Underground Water Conservation District board minutes, 2026-06-26 | Evergreen Underground Water Conservation District | Open |
| 2026-03-16 | HC Capital Partners announces progress of Energy Ranch hyperscale power campus in South Texas, with 250 MW of first power targeted for early 2028 | HC Capital Partners (PR Newswire) | Open |
| 2026-01-06 | HC Capital Partners and Herrmann Family Companies launch "Energy Ranch", a 1,500+ acre power and data infrastructure campus in South Texas | HC Capital Partners (PR Newswire) | Open |
| HC Capital Partners website | HC Capital Partners | Open | |
| Energy Ranch website | HC Capital Partners | Open | |
| Central Registry: regulated entity RN112565122, ENERGY RANCH | Texas Commission on Environmental Quality | Open | |
| Oil & gas investors plan 1,500-acre data center and energy campus outside San Antonio, Texas | Data Center Dynamics | Open |