Yarrington Land
An Austin firm that assembles land and secures the approvals, water and power needed before a site is developed. Through Palomino Alpha, LLC, formed in August 2024, it has a tax abatement agreement with Guadalupe County and a court-approved development agreement, which takes effect once it closes on the land, for a data center campus at Zorn and has applied for water service, a wastewater discharge permit and gas-fired generation interconnections. No builder, operator or tenant for the campus has been named.
- Also known as
- Yarrington Land Holdings, LLC
- Type
- Land acquisition and entitlement developer
- Headquarters
- Austin, Texas
- Ownership
- Privately held. Texas Comptroller records list Matthew Hainline as manager and director of Yarrington Land Holdings LLC, and the Guadalupe County development agreement is signed by Yarrington Land Holdings, LLC as managing member of Palomino Alpha, LLC. No outside investors or end user have been named in the records found.
- Elsewhere in Texas
- The Palomino Alpha site is the only data center project found. A state construction registration lists Yarrington Logistics Owner, LP as owner of Kyle 35 Logistics Park in Kyle, and the tracker Baxtel says Yarrington affiliates developed logistics parks along Interstate 35 there; the tie between that partnership and Yarrington Land Holdings, LLC was not confirmed from a primary record.
Legal entities named in the records: Palomino Alpha, LLC; Yarrington Land Holdings, LLC. Search for these names, not only the company name, in agendas and appraisal records.
1 documented project
- Palomino AlphaProposed · decisions still open
A proposed multi-building data center campus on ranch land at Zorn, beside the LCRA Zorn substation, put together by Austin land firm Yarrington Land through Palomino Alpha, LLC. Guadalupe County granted a ten-year tax abatement in December 2024 and a development agreement in April 2025, and enlarged both to 942.29 acres in February 2026; the water service agreement, the wastewater permit and a lawsuit filed July 20, 2026 against the county are unresolved. The latest dated sources are a San Marcos Daily Record report of October 22, 2026, in which a water district director said the matter seemed dormant for the time being, and ERCOT's report of November 2, 2026, which still lists the company's five gas-fired generation requests at Zorn. Size is stated differently by source: about 365 acres (2025 development agreement), 438.2 acres (2024 zone), about 870 acres (June 2026 water agreement draft; later drafts say about 942) and 942.29 acres (2026 zone); a minimum of 200 MW (abatement agreement), 360 MW (court discussion, March 2025), 480 MW (the company's October 2024 abatement application) and 2,000.5 MW of on-site gas generation requested from ERCOT.
On the record
- The Seguin Gazette reported that allegations about the Guadalupe County Judge's dealings with Palomino Alpha representatives had been referred to the Texas Rangers; DPS said the request was under review. The reported allegations concern the judge's conduct, and no finding has been reported. Source
- The Data Center Action Coalition and three residents sued Guadalupe County, its Commissioners Court and its members to void the Palomino Alpha and CloudBurst approvals, alleging Open Meetings Act, Tax Code and conflict-of-interest violations. The company is not reported as a defendant. Still described as pending litigation on October 22, 2026 (San Marcos Daily Record); Cause No. 26-2397-CV-C, District Court of Guadalupe County. Source
- Crystal Clear Special Utility District tabled the company's request for up to 500,000 gallons of water per day after about three hours of public comment, most of it opposed. The district has not voted on the agreement; a director said in October 2026 that the company had asked for it to be paused. Source
- Guadalupe County Commissioners Court voted 2-2 on the first Palomino Alpha development agreement, so it failed; a revised version passed on April 15, 2025. Source
Sources on the company
| Date | Source | From | Link |
|---|---|---|---|
| 2026-11-02 | Generator Interconnection Status (GIS) Report, October 2026 | ERCOT | Open |
| 2026-06-04 | Hill Country residents push water utility to say no to data center | San Antonio Express-News (via Yahoo News) | Open |
| 2026-03-16 | TPDES application WQ0005514000, administrative package (Palomino Alpha WWTP) | Texas Commission on Environmental Quality | Open |
| 2025-04-15 | Palomino Alpha-Guadalupe County Development Agreement, updated April 10, 2025 | Guadalupe County | Open |
| 2024-01-04 | Project registration TABS2024008602: Kyle 35 Logistics Park Bldg. 1 | Texas Department of Licensing and Regulation | Open |
| Franchise tax account status: Yarrington Land Holdings LLC | Texas Comptroller | Open | |
| Franchise tax account status: Palomino Alpha, LLC | Texas Comptroller | Open | |
| Central Registry: regulated entity RN112394127, Palomino Alpha WWTP | Texas Commission on Environmental Quality | Open | |
| Yarrington Land (tracker listing) | Baxtel | Open |