Medina County / Rio Medina /

Microsoft SAT93 / SAT94 (County Road 381)

Under construction · local approvals doneMicrosoft · Record updated 2026-11-26

Draft record. This page has not yet been checked line by line against the source documents. Treat it as a lead, not a citation.

Microsoft has registered two one-story data center buildings of 245,000 square feet each, SAT93 and SAT94, on County Road 381 in eastern Medina County. Site work started in 2025 under a state stormwater permit covering 140 acres, and the most recent state filings put building construction in 2027 with completion in 2029. No county incentive or county approval for the site was found.

Where this stands and what you can do

The main local decisions have been made and building has started. It is too late to stop this phase. What remains is holding the builder to its permits and agreements, and shaping any later phase or new request.

  1. Report problems as they happen. Dust, mud on roads, runoff, noise and night work are covered by state stormwater and air rules and by local agreements. A dated complaint to the state environmental agency creates a record that is investigated.

    Contact: TCEQ: comment on a pending permit · TCEQ: environmental complaint

  2. Ask that the agreements be enforced. Tax abatement and development agreements carry conditions and reporting duties. Ask the city or county for the compliance reports and what it is doing to check them.

    City council: we do not have a verified contact page for this one yet. Its website will list the members.

    A letter you can copy: ask how the agreements are being enforced

    Send to: City administrator or county judge, with a copy to your council member or commissioner. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Microsoft SAT93 / SAT94 (County Road 381) - compliance with its agreements
    
    Dear [Name],
    
    I live near Microsoft SAT93 / SAT94 (County Road 381) (Microsoft). The project has agreements with [the city / the county] that carry conditions. I would like to know how they are being checked. Please tell me:
    
    1. Which agreements are in force (tax abatement, development agreement, utility service, road use), and where the signed copies can be read.
    2. What the company must report each year, and whether those reports have been received.
    3. Who on staff is responsible for checking compliance, and what happens if a term is missed.
    4. How a resident should report a problem at the site (noise, dust, traffic, water), and to whom.
    
    If this is easier to answer as a public information request, please treat it as one under Government Code chapter 552.
    
    Thank you,
    [Name]
    [Address]
  3. Watch for the next request. Later phases, annexation, more water or sewer, and new abatements each come back for a vote. That is where terms can still be set.

    Contact: Medina County Commissioners Court · how to speak or comment

    A letter you can copy: write to the commissioners court

    Send to: County judge and commissioners. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center development in Medina County - Microsoft SAT93 / SAT94 (County Road 381)
    
    Dear Judge and Commissioners,
    
    I live in Medina County near Microsoft SAT93 / SAT94 (County Road 381) (Microsoft).
    
    I understand the county's power over land use outside city limits is limited. I am asking you to use the authority you do have:
    
    1. Grant no tax abatement or other incentive without a public hearing, published terms, and a clawback.
    2. Use the court's control over county roads to make sure the builder, not county taxpayers, pays for damage from construction traffic.
    3. Apply the county's subdivision, drainage and fire code rules in full, and say publicly which apply to this site.
    4. Post every agreement with a data center developer on the county website.
    5. Ask our state legislators for the authority counties need to set reasonable standards for projects of this size.
    
    Please let me know when the court will next take up an item involving this project.
    
    Thank you,
    [Name]
    [Address]
  4. Ask for the documents. Signed agreements, permits and inspection reports are public records.

    Contact: How to file a public information request

  5. Ask the state and federal governments for standards. Rules on siting, water reporting, on-site power and air pollution are made in Austin and Washington, not at city hall.

    Contact: Who Represents Me (Texas Legislature) · Office of the Texas Governor

    A letter you can copy: write to your state senator and representative

    Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center siting and reporting standards - Medina County
    
    Dear [Senator / Representative] [Name],
    
    I am your constituent in Medina County, where Microsoft SAT93 / SAT94 (County Road 381) (Microsoft) is [proposed / being built / operating] near homes.
    
    I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
    
    1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
    2. Require data centers above a set size to report their water and electricity use each year, publicly.
    3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
    4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
    
    Please tell me your position on these, and whether a bill addressing them is filed or planned.
    
    Thank you,
    [Name]
    [Address - so your office can confirm I am a constituent]

This is general information about how local and state decisions get made, not legal advice.Who decides what, and every contact and letter in one place.

Legal entities
Microsoft Corporation
Also known as
SAT 9394 (TCEQ regulated entity name); County Road 381 datacenter (Microsoft's name); Microsoft San Geronimo campus (Baxtel tracker name); Microsoft La Coste CR 381 (Cleanview tracker name)
Location
County Road 381, north of Potranco Road (FM 1957), east of FM 471
Jurisdiction
Unincorporated Medina County. State filings list Medina County with the San Antonio ZIP code 78253; Microsoft's own page describes the site as in San Antonio. No county or city approval was found on the record. This record files the site under Rio Medina, the nearest named community, following Texas Public Radio; no state filing uses that name.
Investment
Microsoft's registrations with the Texas Department of Licensing and Regulation estimated $350 million for each of two buildings on 2025-02-18 and $26 million for each on 2026-03-09. Texas Public Radio reported the later total as $52 million; the San Antonio Report counted the earlier filings in a $1.4 billion Medina County total.
Water
No water source or volume for this site was found in any record.

Documents and sources

34 items: Government records (20) · Appraisal district records (1) · News and company statements (13)

Government records

Ordinances, resolutions, agreements, notices, permits and filings.

DateDocumentFromLink
2026-11-16Air new source registration 185961, SAT 9394
Pending; applicant Microsoft Corporation, on file since 2026-11-16. Initial project 417452 pending. Site described as north of Potranco Road along County Road 381. The equipment covered was not obtained.
Texas Commission on Environmental QualityOpen
2026-04-06Application of CPS Energy to amend its certificate of convenience and necessity for the proposed Legend Falls 138 kV transmission line project in Medina County (Docket 59549)
Proposes a line of about 1.1 miles from a new Legend Falls substation to STEC's planned San Geronimo substation, which it calls part of the larger Rio Medina Project with Medina Electric Cooperative as the distribution provider. Names no customer. The tracker Baxtel says the San Geronimo substation is planned on Microsoft's land; that was not confirmed in a primary record.
CPS EnergyOpen
2026-03-09TABS2026014456, Microsoft SAT93
Owner Microsoft. "A 1-story, 5-colo building on a new greenfield datacenter site"; 245,000 square feet; $26,000,000; start 2027-03-01, completion 2029-04-30; status Project Registered. Design firm Gensler. The filing does not explain the change from the 2025 estimate.
Texas Department of Licensing and RegulationOpen
2026-03-09TABS2026014461, Microsoft SAT94
Same description and cost as SAT93; start 2027-04-01, completion 2029-05-31; status Project Registered.
Texas Department of Licensing and RegulationOpen
2026-02-02ERCOT independent review scope, STEC Medina County Large Load Project
Regional Planning Group slides. Lists "New San Geronimo Substation" as an STEC project with a July 2027 in-service date and a Rio Medina to Legend Falls line. Names no customer.
ERCOTOpen
2025-09-02Construction stormwater permit TXR1550VS, SAT 9394
Held by Lemartec Corporation; notice of intent approved 2025-09-02. 140 acres disturbed; estimated start 2025-08-25, end 2026-05-29; San Antonio River Basin, segment 1903. The record lists no complaints, investigations or notices of violation.
Texas Commission on Environmental QualityOpen
2025-03-03Request for a docket number: STEC application to amend its certificate of convenience and necessity for the Castroville to Rio Medina to San Geronimo 138-kV transmission line project in Medina County (Docket 57793, item 1)
Opens the transmission line case. Names no customer. The application and later filings were not obtained.
Public Utility Commission of TexasOpen
2025-02-18TABS2025012185, SAT93
Owner Microsoft. County Road 381, "Medina, TX 78253", Medina County. One-story data center building, 245,000 square feet; $350,000,000; start 2025-05-13, completion 2027-06-15; status Review Complete. Design firm Gensler.
Texas Department of Licensing and RegulationOpen
2025-02-18TABS2025012188, SAT94
Same owner, address, size, cost and dates as the SAT93 filing of the same day.
Texas Department of Licensing and RegulationOpen
2024-05-28ERCOT revised notice of endorsement of a Tier 2 transmission project (Project 55999, item 42)
Revised endorsement of the STEC Rio Medina Project.
Public Utility Commission of TexasOpen
2024-05-13Chapter 381 Economic Development Agreement between Medina County, Texas and Microsoft Corporation (fire inspection program)
Approved by Commissioners Court 4-0 on 2024-05-13; Microsoft's signature is dated 2024-07-15. Covers the data centers Microsoft "intends to build" in the county without naming sites. Microsoft pays the county $100,000 a year for three years to fund a fire inspection program; the county is to employ a fire marshal, adopt a fire code and review and issue fire code permits for the data centers, and may not charge Microsoft permitting fees, including fire code fees, during the term. The cover sheet gives a total contract value of $300,000. The recitals state the data centers are not within the corporate limits of a municipality.
Medina CountyOpen
2024-03-05ERCOT notice of endorsement of a Tier 2 transmission project (Project 55999, item 17)
ERCOT's endorsement of the STEC Rio Medina Project with its independent review attached.
Public Utility Commission of TexasOpen
2024-02-12STEC Rio Medina Project, ERCOT independent review status update
Recommends building the Rio Medina and 381Estimate1 138 kV substations, the Castroville to Rio Medina and Rio Medina to 381Estimate1 lines, and upgrades to nearby lines. Names no customer.
ERCOTOpen
2024-01-17STEC Rio Medina Project, ERCOT independent review status update
Regional Planning Group slides. Tier 2 project, estimated at $38.0 million as submitted, in service January 2027, serving a new 129 MW load at the Rio Medina substation. Names no customer.
ERCOTOpen
2023-10-16Overview of STEC Rio Medina Project
Five-page summary of the same proposal: about 13 miles of new 138 kV line from STEC's Castroville substation to a new Rio Medina substation serving a 129 MW load, and on to CPS Energy's system. Names no customer.
South Texas Electric Cooperative (posted by ERCOT)Open
2023-08-18Rio Medina Project, ERCOT Regional Planning Group proposal
Dated 2023-08-18. Names no customer. Besides the Rio Medina load, says "another 129 MW data center load was proposed" at a location that would connect to the proposed line between the Rio Medina substation and a CPS Energy station called 381ESTIMATE1. No document found states that this load is Microsoft's.
South Texas Electric CooperativeOpen
Regulated entity RN112276399, SAT 9394
Central Registry record: primary business data center, county Medina, nearest city San Antonio, ZIP 78253, "29.452888, -98.820660. Located right off of County Road 381". Customers: Microsoft Corporation (owner operator) and Lemartec Corporation (operator). Authorizations: stormwater permit TXR1550VS and air registration 185961.
Texas Commission on Environmental QualityOpen
Data center registry
Checked 2026-11-26: no row names SAT93 or SAT94. Microsoft's Medina County rows are "SAT 80-85" and "SAT 89-90".
Texas ComptrollerOpen
Economic Development page (index of county incentive agreements)
Checked 2026-11-26: lists no agreement for this site. The entry "Hunters Ranch CR 381 South" is a separate agreement for a residential subdivision.
Medina CountyOpen
Legend Falls Substation & Transmission Line Project
Utility project page for the new substation and about two miles of 138 kV corridor in Medina County.
CPS EnergyOpen

Appraisal district records

The county appraisal district page for each parcel: owner, value, deed history.

DateDocumentFromLink
Medina CAD property records for the County Road 381 site
Parcel numbers were not found in any county document. The tracker Baxtel says Microsoft bought about 727 acres fronting County Road 381 in June 2023; that was not checked against a deed or the appraisal roll.
Medina County Appraisal DistrictNot yet archived. Have it?

News and company statements

Reporting and press releases. These are not public records; they are context and leads.

DateDocumentFromLink
2026-06-01Microsoft's datacenter economic impact in San Antonio, TX (FY26 Q4)
Posted June 2026; the day is not given. Company-commissioned figures for Bexar and Medina counties combined; no per-site numbers.
MicrosoftOpen
2026-03-18San Antonio, Medina County continue to attract data centers
Reports the March 2026 filings as two additional buildings "at its location on County Road 381 in the community of Rio Medina" for $52 million, starting that spring. The filings give starts in March and April 2027. County Judge Keith Lutz was not available for comment.
Texas Public RadioRead
2026-03-17Microsoft to invest $52m in data centers in Medina, Texas
Not opened; the site refuses automated requests. Date and content as relayed by Texas Data Center Watch: reports the March 2026 refilings at $26 million each, down from $350 million each, and says it asked Microsoft about the change. Places the site in the town of Medina; the state filings say County Road 381 in Medina County.
Data Center DynamicsRead
2026-01-11Microsoft bets $400M on tiny Texas town with new massive data center
Lists SAT93 and SAT94 among Microsoft's Medina County filings and mentions traffic and water concerns raised in a Redbird Ranch neighborhood group.
MySA (via Yahoo)Read
2025-10-01Microsoft datacenters in Texas (fact sheet)
Posted October 2025; the day is not given. Says Microsoft operates and is building data centers in Bexar and Medina counties, that operating sites employ about 530 people, and that it buys water from SAWS, Yancey Water and the East Medina County Special Utility District in addition to recycled water. Names no individual site.
MicrosoftOpen
2025-08-05County Road 381 datacenter construction update
Says Microsoft is building a datacenter on County Road 381 "in San Antonio, Texas". Construction to begin August 2025 with early works and continue through winter 2028; hours 7 a.m. to 5 p.m. weekdays and 8 a.m. to 5 p.m. Saturdays; vehicles to use County Road 381 and not the subdivision. Contractor Lemartec. Page last modified 2025-12-05.
MicrosoftOpen
2025-03-01As Microsoft doubles down on data centers, Texas officials debate the industry's future
Reports two state filings for buildings along County Road 381 totaling 490,000 square feet, part of a $1.4 billion investment in four Medina County buildings. Says Microsoft's holdings include about 1,112 acres near Castroville and Hondo. Microsoft declined to comment.
San Antonio ReportRead
Data Centers in Medina County, TX
Tracker page with a dated log of the four state filings and Microsoft's notice; notes that the county rests on the state filings.
Texas Data Center Watch (tracker)Read
Microsoft San Geronimo campus
Tracker page. Says the campus sits on about 727 acres bought in June 2023, about three miles northwest of Microsoft's Texas Research Park campus, that Medina Electric Cooperative provides retail service, and that STEC plans its San Geronimo substation on the land. Not checked against a primary record.
Baxtel (tracker)Read
Microsoft: SAT93
Tracker page. Says site clearing began in 2025 and mass grading continued through 2026, with vertical construction starting in 2027.
Baxtel (tracker)Read
Microsoft La Coste CR 381 (SAT93-94)
Tracker page for the site.
Cleanview (tracker)Read
Microsoft Castroville Campus Data Centers
Aggregator profile of all four Microsoft addresses in the county. Repeats figures from the state filings and news reports.
Blackridge Research (tracker)Read
Greater San Antonio community page
Company page for the region. States that Microsoft operates data centers in Bexar and Medina counties and links its construction updates.
MicrosoftOpen

Timeline

  1. Texas Commission on Environmental Quality. Microsoft Corporation's air new source registration 185961 for the site entered the registry as pending. Source
  2. Texas Department of Licensing and Regulation. Microsoft filed new registrations for SAT93 and SAT94, each "a 1-story, 5-colo building on a new greenfield datacenter site": $26 million each, starts 2027-03-01 and 2027-04-01, completions 2029-04-30 and 2029-05-31. Source
  3. Texas Commission on Environmental Quality. Construction stormwater coverage TXR1550VS began for "SAT 9394", held by Lemartec Corporation: 140 acres disturbed, estimated start 2025-08-25, estimated end 2026-05-29. Source
  4. Microsoft. Published a construction notice for the County Road 381 site: work to begin August 2025 and run through winter 2028, with construction traffic entering from County Road 381 and not through the subdivision. Names Lemartec as contractor. Source
  5. Texas Department of Licensing and Regulation. Microsoft registered SAT93 and SAT94 on County Road 381: one-story buildings of 245,000 square feet, $350 million each, start 2025-05-13, completion 2027-06-15. Source

See an error or have a document that belongs here? Tell us.