Microsoft
Microsoft has built data centers in the San Antonio area since 2007 and now owns seven sites in Bexar County and three campuses in Medina County, all held in the name of Microsoft Corporation. It also occupies halls owned by CyrusOne and Stream Data Centers in San Antonio, and the state registry lists it as an occupant of leased buildings in Irving and the Austin area. Its 2021 Chapter 381 tax agreement with Medina County was ended by mutual agreement in 2026.
- Also known as
- Microsoft Corporation; MSFT; Microsoft Azure
- Type
- Hyperscale cloud operator (owns and leases data centers)
- Headquarters
- Redmond, Washington
- Ownership
- Publicly traded (Nasdaq: MSFT). In Texas records the owner, occupant and operator is Microsoft Corporation itself; no separate project LLC appears in the state data center registry, TCEQ registrations or the Medina County agreements.
- Elsewhere in Texas
- Bexar County: seven owned sites (Westover Hills SN1/SN2, SN4, SN7, SAT14, SAT15-17, the Texas Research Park campus and Sentry Gateway). Medina County: three campuses (FM 1957 at FM 471, SAT89/90 on US 90, and SAT93/94 on County Road 381). Microsoft's October 2025 Texas fact sheet says it operates and is building only in Bexar and Medina counties and employs about 530 people there. The Texas Comptroller's data center registry also lists Microsoft as occupant of buildings it does not own: CyrusOne's San Antonio Data Center II (2016) and III (2017), Stream's SDC SATB1 (2024), Vantage's TX11 (2024-03-06 to 2025-11-04, since re-registered with Oracle as occupant), QTS Irving DC3 and QTS Irving 1 in Irving (2024), and EdgeConneX's ECX AUS11-16 (2026). Incentives on record: a 10-year, 100% City of San Antonio abatement (2007); a 15-year City of San Antonio Chapter 380 grant (2013); a Medina County Chapter 381 agreement for 80% of county taxes (2021, terminated effective 2026-08-12); a Medina County fire inspection agreement (2024); and eight registrations for the state sales tax exemption between 2013 and 2024. The Comptroller's Chapter 312 abatement registry has no Microsoft entry.
- Website
- local.microsoft.com
Legal entities named in the records: COPT San Antonio II, L.P.; Chevron U.S.A. Inc. (prior owner); Microsoft Corporation; Westover RTF 2 LP (owner before Chevron, per the appraisal district). Search for these names, not only the company name, in agendas and appraisal records.
10 documented projects
- 3823 Wiseman Blvd (SN4)
A single data center building beside Microsoft's original Rogers Road site, built under a 2013 city incentive agreement. The appraisal district lists the building as built in 2014 with a 2016 addition; the tracker Baxtel says it opened in 2015. The city agreed to reimburse at least 40 percent of the city property taxes on the new investment for 15 years in return for $250 million of investment and 20 jobs. The Bexar Appraisal District lists 277,745 square feet and a 2026 improvement value of $110 million; its land account, covering Lots 4 and 5, is 25.54 acres.
- Microsoft Castroville campus (SAT80, SAT81, SAT82)
Microsoft's first Medina County data center campus sits on 206.18 acres at Potranco Road (FM 1957) and FM 471, north of Castroville. State filings made in 2023 gave completion dates of August and September 2024 for two buildings, SAT80 and SAT81, and show their inspections as complete; a third, SAT82, is registered under two different addresses with completion in 2028. No state or county record found says the buildings are in service; Microsoft says it operates data centers in Medina County without naming sites. Medina County granted an 80% county tax incentive in 2021 and ended it by mutual agreement in 2026.
- Microsoft SAT89/90 Data CenterUnder construction · local approvals done
Two single-story data center buildings, SAT89 and SAT90, are under construction on a platted lot on the north side of US 90 west of Castroville, next to the CyrusOne and Tract sites. Medina County approved the plat in November 2023 and site work began in early 2024. State environmental records show four complaints about dust and stormwater in 2024 and two notices of violation to the site contractor, both resolved.
- Microsoft SAT93 / SAT94 (County Road 381)Under construction · local approvals done
Microsoft has registered two one-story data center buildings of 245,000 square feet each, SAT93 and SAT94, on County Road 381 in eastern Medina County. Site work started in 2025 under a state stormwater permit covering 140 acres, and the most recent state filings put building construction in 2027 with completion in 2029. No county incentive or county approval for the site was found.
- Rogers Road SN7
A data center building that the tracker Baxtel and the San Antonio Report say Stream Data Centers first developed. The appraisal district shows it passed from Westover RTF 2 LP to Chevron in July 2011 and from Chevron to Microsoft by deed dated 31 October 2017, for a reported $80 million. Microsoft registered three data halls (colos) with the state in 2019, with estimated completion dates of December 2019 and September 2021; the appraisal district lists 93,100 square feet built in 2020. The Bexar Appraisal District lists 296,874 square feet on 33.44 acres and a 2026 market value of $125 million.
- Sentry Gateway Data Center
A data center on a 28-acre lot owned by COPT San Antonio II, L.P., which state construction filings call EX West Green Data Center and TCEQ registers as Sentry Gateway Data Center with Microsoft Corporation as owner and operator. The site appears to be in operation: the appraisal district lists data center modules built 2019-2022, the state construction filings for both phases are closed, and TCEQ lists Microsoft as owner and operator with active air and tank registrations (air registration last revised June 2025). Microsoft also owns two adjoining lots (properties 1142335 and 1177240); the appraisal district dropped the improvement value on one of them from $17.5 million in 2025 to $0 in 2026, and neither shows a building in the 2026 appraisal records.
- Texas Research Park campus (SAT09-13, SAT40, SAT46)
Microsoft's campus in Texas Research Park, on land bought in December 2015 and built out since 2016. The Bexar Appraisal District lists 115.6 acres and about 1 million square feet in Bexar County; the 2015 purchase was reported as 158 acres, and a tracker (Baxtel) puts a further 55.5 acres in Medina County. The tracker Cleanview lists 409 MW of operating capacity for the campus; no utility, permit or company figure was found.
- Westover Hills SN1/SN2
Microsoft's first San Antonio data center: two buildings on about 36 acres per the appraisal district (the 2007 abatement described 44 acres) at 5150 Rogers Road, approved for city incentives in January 2007 and opened in 2008 according to Data Center Knowledge. The city granted a 10-year, 100 percent property tax abatement and CPS Energy was asked for up to $5.2 million toward electrical infrastructure. The Bexar Appraisal District lists 463,350 square feet and a 2026 market value of $112 million.
- Westover Link SAT15-17
A planned three-building campus at State Highway 151 and Westover Link, on about 71 acres by the county parcel map (the appraisal district's land lines total about 76 acres). SAT15 was registered with the state in 2022 and holds active air permits. No record opened states that any building is in service: SAT15's state filing shows its inspection complete and the tracker Baxtel says its first colos came online in 2025. SAT16 and SAT17 were registered in 2024 with estimated completion dates of December 2025 and December 2027, and nothing opened shows either complete. The Bexar Appraisal District lists one 256,800-square-foot building and a 2026 market value of $65 million.
- Wiseman Blvd SAT14
Two data center buildings on about 33.6 acres in a subdivision platted as Valero Data Expansion II; the tracker Baxtel says Microsoft bought the land from Valero in late 2020. No record opened states when the buildings entered service: the appraisal district lists both as built in 2022, the state filings for the fit-out phases show inspections complete with an estimated completion of 31 March 2026, and Baxtel says the first colos came online in 2024. The city's staff and Development Services director denied Microsoft's request to remove more trees than the tree ordinance allows; the Planning Commission overturned that 6-1 and the City Council affirmed it 8-3 in January 2022, allowing the removal of 2,157 of the site's 2,226 significant and heritage trees by the city memo's count (2,642 trees in all, according to the San Antonio Report). The Bexar Appraisal District lists 260,384 square feet and a 2026 market value of $65 million.
On the record
- Virginia: the Department of Environmental Quality proposed a consent order with a civil penalty of nearly $2.5 million for Microsoft's Leesburg data center at 19515 Compass Creek Parkway, finding it exceeded permit limits for diesel fuel use and for nitrogen oxides, particulate matter and volatile organic compounds while running backup generators during a substation outage from 2025-06-27 to 2025-07-01. The order was open for public comment until October 14; whether it was finalized was not established. Microsoft said DEQ's emissions calculations were not as accurate as they should be and that it spent about $31 million to prevent another extended outage. DEQ's news bulletin of 2026-10-05 describes it as a nearly $2.5 million settlement and does not say whether the order is final. Source
- Wisconsin: three Sturtevant residents filed a proposed class action against Microsoft in U.S. District Court for the Eastern District of Wisconsin, alleging nuisance and negligence from noise at its Mount Pleasant data center. Microsoft said its noise levels met the local ordinance and that it had added mitigations in April and June 2026; a village spokesperson said no formal complaints had been received since mid-April. Source
- Wisconsin: Microsoft withdrew a proposed 244-acre data center site in Caledonia after residents opposed the rezoning. Its statement: "Based on the community feedback we heard, we have chosen not to move forward with this site." Source
- Wisconsin: Midwest Environmental Advocates, for Milwaukee Riverkeeper, sued the City of Racine under the state public records law for not releasing projected water use for Microsoft's Mount Pleasant data center. Microsoft was not a party; a spokesperson told Spectrum News most of the campus would use a zero-water cooling design. No outcome was found. Source
- The San Antonio Current reported, citing a study by Techie + Gamers magazine that used San Antonio Water System data, that a Microsoft data center and an Army Corps of Engineers data center in San Antonio together used 463 million gallons of water in 2023 and 2024. The article does not say which Microsoft facility. Microsoft's October 2025 fact sheet says one Texas data center was still cooled with potable water and was being moved to reused water. Source
- TCEQ issued a notice of violation to the stormwater permit holder at Microsoft's SAT89/90 construction site near Castroville (the contractor, not Microsoft) for failing to post a construction site notice, and a second on 2024-09-09 for a stormwater control not kept in working condition. Both are shown as resolved. TCEQ logged four dust and stormwater complaints about the site in 2024. Details are on this site's SAT89/90 record.
- San Antonio City Council voted 8-3 to uphold a Planning Commission decision letting Microsoft remove 2,642 trees at its SAT14 site, more than the tree ordinance allows, after city staff and the Development Services director had denied the request. Microsoft agreed to a mitigation payment and 833 replacement trees. Details and documents are on this site's SAT14 record.
Sources on the company
| Date | Source | From | Link |
|---|---|---|---|
| 2026-10-05 | DEQ News (bulletin of 2026-10-05) | Virginia Department of Environmental Quality | Open |
| 2026-09-15 | Microsoft ordered nearly $2.5M fine for air pollution from Northern Virginia data center | WJLA | Open |
| 2026-08-13 | Governor Abbott Announces Microsoft, Hut 8 And Equinix Commit To Comply With His Data Center Standards | Office of the Texas Governor | Open |
| 2026-08-12 | Agreement to Terminate the Chapter 381 Agreement between Microsoft Corporation and Medina County | Medina County | Open |
| 2026-07-02 | Microsoft sued over noise complaints at new Mount Pleasant data center | Wisconsin Public Radio | Open |
| 2026-06-01 | Microsoft's datacenter economic impact in San Antonio, TX (FY26 Q4) | Microsoft | Open |
| 2026-01-13 | Building Community-First AI Infrastructure | Microsoft (Brad Smith, Vice Chair and President) | Open |
| 2025-10-08 | Data center in Caledonia; Microsoft shuts down plans to build | FOX6 Milwaukee | Open |
| 2025-10-01 | Microsoft datacenters in Texas | Microsoft | Open |
| 2025-09-16 | Environmental group sues Racine over Microsoft data center water records | Spectrum News 1 Wisconsin | Open |
| 2025-07-30 | San Antonio data centers guzzled 463 million gallons of water as area faced drought | San Antonio Current | Open |
| 2024-05-13 | Chapter 381 agreement: Microsoft fire code inspection program | Medina County | Open |
| 2023-08-07 | Number of Microsoft data centers in San Antonio region starting to add up | San Antonio Report | Open |
| 2021-07-13 | Chapter 381 Agreement between Microsoft Corporation and Medina County (FM 1957 / FM 471) | Medina County | Open |
| 2013-11-21 | Ordinance 2013-11-21-0817 and Chapter 380 grant agreement with Microsoft Corporation | City of San Antonio | Open |
| Qualifying data center and large data center project registries | Texas Comptroller of Public Accounts | Open | |
| Chapter 312 tax abatement registry (detail file) | Texas Comptroller of Public Accounts | Open | |
| Microsoft in your community: Greater San Antonio | Microsoft | Open |