Companies /

Microsoft

Draft record. This page has not yet been checked line by line against its sources. Treat it as a lead, not a citation.

Microsoft has built data centers in the San Antonio area since 2007 and now owns seven sites in Bexar County and three campuses in Medina County, all held in the name of Microsoft Corporation. It also occupies halls owned by CyrusOne and Stream Data Centers in San Antonio, and the state registry lists it as an occupant of leased buildings in Irving and the Austin area. Its 2021 Chapter 381 tax agreement with Medina County was ended by mutual agreement in 2026.

Also known as
Microsoft Corporation; MSFT; Microsoft Azure
Type
Hyperscale cloud operator (owns and leases data centers)
Headquarters
Redmond, Washington
Ownership
Publicly traded (Nasdaq: MSFT). In Texas records the owner, occupant and operator is Microsoft Corporation itself; no separate project LLC appears in the state data center registry, TCEQ registrations or the Medina County agreements.
Elsewhere in Texas
Bexar County: seven owned sites (Westover Hills SN1/SN2, SN4, SN7, SAT14, SAT15-17, the Texas Research Park campus and Sentry Gateway). Medina County: three campuses (FM 1957 at FM 471, SAT89/90 on US 90, and SAT93/94 on County Road 381). Microsoft's October 2025 Texas fact sheet says it operates and is building only in Bexar and Medina counties and employs about 530 people there. The Texas Comptroller's data center registry also lists Microsoft as occupant of buildings it does not own: CyrusOne's San Antonio Data Center II (2016) and III (2017), Stream's SDC SATB1 (2024), Vantage's TX11 (2024-03-06 to 2025-11-04, since re-registered with Oracle as occupant), QTS Irving DC3 and QTS Irving 1 in Irving (2024), and EdgeConneX's ECX AUS11-16 (2026). Incentives on record: a 10-year, 100% City of San Antonio abatement (2007); a 15-year City of San Antonio Chapter 380 grant (2013); a Medina County Chapter 381 agreement for 80% of county taxes (2021, terminated effective 2026-08-12); a Medina County fire inspection agreement (2024); and eight registrations for the state sales tax exemption between 2013 and 2024. The Comptroller's Chapter 312 abatement registry has no Microsoft entry.
Website
local.microsoft.com

Legal entities named in the records: COPT San Antonio II, L.P.; Chevron U.S.A. Inc. (prior owner); Microsoft Corporation; Westover RTF 2 LP (owner before Chevron, per the appraisal district). Search for these names, not only the company name, in agendas and appraisal records.

10 documented projects

On the record

Lawsuits, violations, fines and disputes reported about this company, each with its source. An allegation is described as one; it is not a finding.

  1. Virginia: the Department of Environmental Quality proposed a consent order with a civil penalty of nearly $2.5 million for Microsoft's Leesburg data center at 19515 Compass Creek Parkway, finding it exceeded permit limits for diesel fuel use and for nitrogen oxides, particulate matter and volatile organic compounds while running backup generators during a substation outage from 2025-06-27 to 2025-07-01. The order was open for public comment until October 14; whether it was finalized was not established. Microsoft said DEQ's emissions calculations were not as accurate as they should be and that it spent about $31 million to prevent another extended outage. DEQ's news bulletin of 2026-10-05 describes it as a nearly $2.5 million settlement and does not say whether the order is final. Source
  2. Wisconsin: three Sturtevant residents filed a proposed class action against Microsoft in U.S. District Court for the Eastern District of Wisconsin, alleging nuisance and negligence from noise at its Mount Pleasant data center. Microsoft said its noise levels met the local ordinance and that it had added mitigations in April and June 2026; a village spokesperson said no formal complaints had been received since mid-April. Source
  3. Wisconsin: Microsoft withdrew a proposed 244-acre data center site in Caledonia after residents opposed the rezoning. Its statement: "Based on the community feedback we heard, we have chosen not to move forward with this site." Source
  4. Wisconsin: Midwest Environmental Advocates, for Milwaukee Riverkeeper, sued the City of Racine under the state public records law for not releasing projected water use for Microsoft's Mount Pleasant data center. Microsoft was not a party; a spokesperson told Spectrum News most of the campus would use a zero-water cooling design. No outcome was found. Source
  5. The San Antonio Current reported, citing a study by Techie + Gamers magazine that used San Antonio Water System data, that a Microsoft data center and an Army Corps of Engineers data center in San Antonio together used 463 million gallons of water in 2023 and 2024. The article does not say which Microsoft facility. Microsoft's October 2025 fact sheet says one Texas data center was still cooled with potable water and was being moved to reused water. Source
  6. TCEQ issued a notice of violation to the stormwater permit holder at Microsoft's SAT89/90 construction site near Castroville (the contractor, not Microsoft) for failing to post a construction site notice, and a second on 2024-09-09 for a stormwater control not kept in working condition. Both are shown as resolved. TCEQ logged four dust and stormwater complaints about the site in 2024. Details are on this site's SAT89/90 record.
  7. San Antonio City Council voted 8-3 to uphold a Planning Commission decision letting Microsoft remove 2,642 trees at its SAT14 site, more than the tree ordinance allows, after city staff and the Development Services director had denied the request. Microsoft agreed to a mitigation payment and 833 replacement trees. Details and documents are on this site's SAT14 record.

Sources on the company

DateSourceFromLink
2026-10-05DEQ News (bulletin of 2026-10-05)
Describes a nearly $2.5 million settlement with Microsoft over air violations at its Leesburg data center as the largest civil penalty DEQ has secured from a data center. Does not say whether the consent order is final.
Virginia Department of Environmental QualityOpen
2026-09-15Microsoft ordered nearly $2.5M fine for air pollution from Northern Virginia data center
Proposed Virginia DEQ consent order for the Leesburg data center: about 1,190,000 gallons of fuel against a 665,850-gallon limit and about 102 tons of nitrogen oxides against a 94.67-ton limit over twelve months. The headline says nearly $3 million and the text roughly $2.5 million. The DEQ order itself was not obtained.
WJLAOpen
2026-08-13Governor Abbott Announces Microsoft, Hut 8 And Equinix Commit To Comply With His Data Center Standards
The Governor's office says Microsoft will comply with his standards: pay for its own electric infrastructure, reuse water, and disclose incentives, water sources and use, neighbor-impact measures and ownership to the PUC and ERCOT. No statement from Microsoft is included.
Office of the Texas GovernorOpen
2026-08-12Agreement to Terminate the Chapter 381 Agreement between Microsoft Corporation and Medina County
Ends the 2021 agreement by mutual agreement effective 2026-08-12 and states neither party was in default. The Commissioners Court approved it 4-0 on 2026-09-08. No reason is given in the document.
Medina CountyOpen
2026-07-02Microsoft sued over noise complaints at new Mount Pleasant data center
Proposed class action by three Sturtevant residents over generator and cooling equipment noise; includes Microsoft's statement and the village's comment.
Wisconsin Public RadioOpen
2026-06-01Microsoft's datacenter economic impact in San Antonio, TX (FY26 Q4)
Company figures for Bexar and Medina counties combined, as summarized in this site's facility records: 635 direct jobs in 2025 and $48.4 million in incremental tax revenue in 2025. Published June 2026; day not given.
MicrosoftOpen
2026-01-13Building Community-First AI Infrastructure
Company pledge for U.S. data centers: to ask utilities to set rates that cover its costs so residential bills do not rise; a 40% improvement in water-use intensity by 2030; to replenish more water than it uses in the same water districts; to publish water use for each U.S. data center region; and not to ask municipalities to reduce local property tax rates.
Microsoft (Brad Smith, Vice Chair and President)Open
2025-10-08Data center in Caledonia; Microsoft shuts down plans to build
Seen in search results, not opened; the withdrawal and Microsoft's statement are reported consistently by several Wisconsin outlets.
FOX6 MilwaukeeOpen
2025-10-01Microsoft datacenters in Texas
Company fact sheet, published October 2025 (day not given). Says Microsoft operates and is building in Bexar and Medina counties; about 530 employees; most existing facilities use air-cooled chillers and "only a fraction" use water-cooled chillers; most water-cooled chillers in Texas use reused water and the one data center using potable water for cooling "is transitioning to reused water"; water is bought from SAWS, Yancey Water and the East Medina County Special Utility District; backup generators run on a renewable biofuel; renewable power purchase agreements are named. No volumes are given.
MicrosoftOpen
2025-09-16Environmental group sues Racine over Microsoft data center water records
Public records suit against the City of Racine, not Microsoft. Title paraphrased.
Spectrum News 1 WisconsinOpen
2025-07-30San Antonio data centers guzzled 463 million gallons of water as area faced drought
SAWS figures for two data centers combined, one of them Microsoft's; the facility is not identified.
San Antonio CurrentOpen
2024-05-13Chapter 381 agreement: Microsoft fire code inspection program
Microsoft pays the county $100,000 a year for three years toward a fire inspection program; the county may not charge Microsoft permitting fees during the term.
Medina CountyOpen
2023-08-07Number of Microsoft data centers in San Antonio region starting to add up
Counts at least eight Microsoft properties in Bexar and Medina counties from state filings and more than $1.2 billion in estimated investment; Microsoft did not respond to the outlet's questions.
San Antonio ReportOpen
2021-07-13Chapter 381 Agreement between Microsoft Corporation and Medina County (FM 1957 / FM 471)
80% of county taxes other than debt service through 2038 on a 206.18-acre site, tied to a $400 million minimum investment and 20 jobs. Summarized from this site's facility record for the Castroville campus.
Medina CountyOpen
2013-11-21Ordinance 2013-11-21-0817 and Chapter 380 grant agreement with Microsoft Corporation
15-year grant of 40% to 63% of city property taxes on a $250 million investment with 20 jobs; recites the 2007 10-year, 100% abatement for the first Westover Hills data center. Taken from this site's SN4 record; not re-read for this company record.
City of San AntonioOpen
Qualifying data center and large data center project registries
State sales tax exemption registry. Rows with Microsoft Corporation as owner: "Microsoft Corporation" DC993797 (2013-12-01, ends 2028-12-01), "NADC" DC718710 (2013-09-01, ended 2023-09-01), "Microsoft San Antonio (SAT14)" DC969263 (2021-08-18), "Microsoft Corporation (SAT09 - SAT13)" LD727073 (2015-12-15, ends 2035-12-15), "(SAT 15-17)" LD371323 (2023-04-04), "(SAT 80-85)" LD384204 (2022-03-31), "(SAT 89-90)" LD772702 (2024-04-04). Rows with Microsoft as occupant only: CyrusOne San Antonio Data Center II and III, SDC SATB1, TX11 Data Center, QTS Irving DC3, QTS Irving 1, ECX AUS11-16. The registry gives no addresses.
Texas Comptroller of Public AccountsOpen
Chapter 312 tax abatement registry (detail file)
Searched for Microsoft; no rows. Chapter 380 and 381 agreements are not reported in this file.
Texas Comptroller of Public AccountsOpen
Microsoft in your community: Greater San Antonio
Company page for the region. Lists its five community commitments and links its Texas fact sheets and construction notices. Gives no water, power or tax figures.
MicrosoftOpen

Record updated 2026-11-27