| 2026-08-13 | Construction stormwater permit TXR1528ZD, SAT89 Held by W.G. Yates & Sons Construction Co.; active since 2026-08-13. 102 acres disturbed; estimated start 2025-12-15, end 2028-03-08; receiving water Chacon Creek. The record lists no complaints, investigations or notices of violation. | Texas Commission on Environmental Quality | Open |
| 2026-07-21 | Status update: combined CPS Energy Large Load Additions Project and STEC Medina County Large Load Project Regional Planning Group slides. Lists "Dunlay substation" as an STEC Tier 2 project with an April 2026 in-service date, and a proposed 138 kV path from Pearson to Dunlay to a new Alsatian station to Bader to Castroville. Names no customer. | ERCOT | Open |
| 2026-01-31 | Air new source registration 182887L001, SAT89 Active; held by Iva Materials LLC since 2026-01-31. Initial project 404537 completed 2026-02-20. The record does not describe the equipment. | Texas Commission on Environmental Quality | Open |
| 2026-01-13 | Air new source registration 182686 Active; held by Microsoft Corporation since 2026-01-13. Initial project 403435 completed 2026-02-09. The equipment covered was not obtained from TCEQ; the tracker Baxtel describes it as sixty 3.1 MW diesel generators plus two 500 kW units. The two 2024 dust complaints are listed under this registration. | Texas Commission on Environmental Quality | Open |
| 2025-09-22 | Notice of public hearing regarding the designation of CyrusOne Reinvestment Zone 1 (legal description) The neighboring CyrusOne zone's legal description calls out the adjoining 123.729-acre tract "described to Microsoft Corporation as recorded in Document No. 2021010757". | Medina County | Open |
| 2025-02-25 | TABS2025012765, SAT89/90 Data Center Owner Microsoft Corporation. 2995 US Hwy 90 W, Castroville. Two single-story data center buildings each with five colos plus campus site work; about 489,400 square feet; $765,000,000; start 2025-06-01, completion 2027-07-31; status Review Complete. Design firm WSP USA. | Texas Department of Licensing and Regulation | Open |
| 2024-09-09 | Notices of violation under stormwater permit TXR1532PU Two notices, both classed moderate and resolved: 2024-04-02, failure to post a TCEQ construction site notice (30 TAC 281.25(a)(4); permit Part III.D.2); 2024-09-09, failure to maintain a protective measure identified in the stormwater pollution prevention plan in effective operating condition. | Texas Commission on Environmental Quality | Open |
| 2024-05-13 | Chapter 381 Economic Development Agreement between Medina County, Texas and Microsoft Corporation (fire inspection program) Approved by Commissioners Court 4-0 on 2024-05-13; Microsoft's signature is dated 2024-07-15. Covers the data centers Microsoft "intends to build" in the county without naming sites. Microsoft pays the county $100,000 a year for three years to fund a fire inspection program; the county is to employ a fire marshal, adopt a fire code and review and issue fire code permits for the data centers, and may not charge Microsoft permitting fees, including fire code fees, during the term. The cover sheet gives a total contract value of $300,000. The recitals state the data centers are not within the corporate limits of a municipality. | Medina County | Open |
| 2024-05-06 | Investigations under stormwater permit TXR1532PU Four compliance investigations: 2024-02-06, 2024-03-13, 2024-04-18 and 2024-05-06. The investigation reports were not obtained. | Texas Commission on Environmental Quality | Open |
| 2024-04-22 | Complaint 422071 (stormwater) The complainant alleged sediment-laden stormwater ran onto their property from the construction site. Investigation 1995771 on 2024-05-06 led to the 2024-09-09 notice of violation, resolved 2024-09-27. Closed 2024-06-28. | Texas Commission on Environmental Quality | Open |
| 2024-04-05 | Complaint 420966 (dust) Dust complaint. Investigation 1975966 on 2024-04-18. No notice of violation or enforcement issued. Closed 2024-04-18. | Texas Commission on Environmental Quality | Open |
| 2024-04-04 | Data center registry Row "Microsoft Corporation (SAT 89-90)": effective 04/04/2024; owner, occupant and operator Microsoft Corporation; registration LD772702. | Texas Comptroller | Open |
| 2024-03-11 | Complaint 418601 (dust) Dust complaint. Investigation 1972565 on 2024-03-13. No notice of violation or enforcement issued. Closed 2024-04-01. | Texas Commission on Environmental Quality | Open |
| 2024-02-01 | Construction stormwater permit TXR1532PU Held by Lemartec Corporation; notice of intent approved 2024-02-01. 84 acres disturbed; estimated start 2024-02-05, end 2024-05-31; receiving water Chacon Creek; coordinates 29.35138, -98.93942. Still shown as active. | Texas Commission on Environmental Quality | Open |
| 2024-01-30 | Complaint 416714 (stormwater) Two complainants alleged a 125-acre lot was being developed without a stormwater pollution prevention plan, with no silt fencing to keep runoff from the creek and mud tracked out at the entrance. Investigation 1961232 on 2024-02-06 led to the 2024-04-02 notice of violation for failure to post a construction site notice, shown as resolved 2024-03-19. Closed 2024-03-25. | Texas Commission on Environmental Quality | Open |
| 2023-11-27 | Vacate and replat creating Lot 1, SAT 89 (commercial development plat) Pages 34-35 of the agenda packet. Owner Microsoft Corporation; 123.68 acres in the Nepocino Flores survey, out of a called 123.729-acre tract (document 2021010757). A surveyor's note says the property is all of appraisal district parcel 12988. Shows a Medina Electric Cooperative easement and flood zones X and A. Engineer Walter P Moore. | Medina County | Open |
| 2023-11-16 | TxDOT plat review letter, US-90 Page 36 of the agenda packet. No objection to the plat for "Microsoft Corporation" on US-90 westbound about 2.35 miles west of FM 1343. Requires plat notes on noise set-back, driveway permits and a right-of-way reservation. | Texas Department of Transportation | Open |
| 2023-10-16 | Overview of STEC Rio Medina Project Five-page summary of the same proposal: about 13 miles of new 138 kV line from STEC's Castroville substation to a new Rio Medina substation serving a 129 MW load, and on to CPS Energy's system. Names no customer. | South Texas Electric Cooperative (posted by ERCOT) | Open |
| 2023-08-18 | Rio Medina Project, ERCOT Regional Planning Group proposal Dated 2023-08-18. Names no customer. Says STEC studied a second 129 MW data center load that would connect to the 138 kV line between the Pearson and Bader substations, and that Medina Electric Cooperative requested a substation named Dunlay for it. Dunlay is on US 90 west of this site; no document found states that the Dunlay load is Microsoft's. | South Texas Electric Cooperative | Open |
| Regulated entity RN111896825, Microsoft SAT 8990 Data Center Project Site Central Registry record: north of Hwy 90 and south of County Road 4516, nearest city Castroville. Customers: Microsoft Corporation (owner operator) and Lemartec Corporation (operator). Authorizations: air registration 182686 and stormwater permit TXR1532PU. | Texas Commission on Environmental Quality | Open |
| Regulated entity RN112509039, SAT89 Second Central Registry record at 2995 US 90 West, Castroville, for contractor W.G. Yates & Sons Construction Co. One authorization: stormwater permit TXR1528ZD. | Texas Commission on Environmental Quality | Open |
| Regulated entity RN112368550, SAT89 Third Central Registry record, located by a site entrance on the north side of Hwy 90 about 3.6 miles west of Castroville. Customer Iva Materials LLC (operator). One authorization: air registration 182887L001. | Texas Commission on Environmental Quality | Open |
| Economic Development page (index of county incentive agreements) Checked 2026-11-26: lists no tax agreement for this site. The only Microsoft tax agreement listed is the terminated FM 1957 / FM 471 agreement. | Medina County | Open |
| Non-standard water service agreement between East Medina County Special Utility District and Microsoft Not obtained. The district's superintendent told the San Antonio Report in August 2024 that terms were being worked out for the Highway 90 site. Whether the board has approved an agreement was not confirmed. | East Medina County Special Utility District | Not yet archived. Have it? |