Cities /
Data centers in and near Castroville
4 documented facilities in Medina County.
- Medina County Data Center (SAT14)Under construction · local approvals done
A CyrusOne data center campus on about 244.3 acres along US 90 west of Castroville, next to Microsoft's US 90 site. Medina County designated the land a reinvestment zone in September 2025 and approved an 80 percent, 10-year county tax abatement in November 2025; CyrusOne paid the county $5 million toward County Road 4516. The first building, SAT14A, is under construction, and state records list three notices of violation in 2026 under the construction stormwater permit held by the contractor, PCL Construction Services, Inc., all shown as resolved.
- Medina Technology ParkProposed · decisions still open
A 265-acre site off County Road 4516 west of Castroville that Tract is preparing for a 500 MW data center, with power to come through a new South Texas Electric Cooperative substation. No county or city approval has been recorded. The developer is before the Public Utility Commission challenging how ERCOT ranked the project's grid connection, and in November 2026 a contractor obtained a state construction stormwater permit for a site named "Substation - STECTRACT" on County Road 4516, whose coordinates fall inside the boundary Tract publishes; the permit does not name Tract.
- Microsoft Castroville campus (SAT80, SAT81, SAT82)
Microsoft's first Medina County data center campus sits on 206.18 acres at Potranco Road (FM 1957) and FM 471, north of Castroville. State filings made in 2023 gave completion dates of August and September 2024 for two buildings, SAT80 and SAT81, and show their inspections as complete; a third, SAT82, is registered under two different addresses with completion in 2028. No state or county record found says the buildings are in service; Microsoft says it operates data centers in Medina County without naming sites. Medina County granted an 80% county tax incentive in 2021 and ended it by mutual agreement in 2026.
- Microsoft SAT89/90 Data CenterUnder construction · local approvals done
Two single-story data center buildings, SAT89 and SAT90, are under construction on a platted lot on the north side of US 90 west of Castroville, next to the CyrusOne and Tract sites. Medina County approved the plat in November 2023 and site work began in early 2024. State environmental records show four complaints about dust and stormwater in 2024 and two notices of violation to the site contractor, both resolved.
