Draft record. This page has not yet been checked line by line against its sources. Treat it as a lead, not a citation.

Tract is a Denver-based company that buys large sites, arranges zoning, power and water for them, and markets them to data center operators as technology parks. It does not usually build or run the data centers itself. In Texas its land is held through LLCs with names beginning TXLCO and its grid request near Castroville is in the name of Medina County Power NR I, LLC.

Also known as
Tract Capital Management, LP; Tract Management Company LP; TXLCO Bexar County LLC; TXLCO Bexar County Two LLC; TXLCO San Antonio LLC; Medina County Power NR I, LLC
Type
Land and power developer
Headquarters
Denver, Colorado
Ownership
Privately held. Columbia Capital lists Tract among its current portfolio companies. Other investors and a founder are named in trade coverage and deal trackers that were not opened for this record and are not confirmed here; no ownership percentages were found.
Elsewhere in Texas
Beyond the three sites on this index (I-35 Technology Park near Lytle and Applewhite Technology Park in San Antonio, both Bexar County, and Medina Technology Park near Castroville, Medina County), Tract bought 1,515.9 acres in Caldwell County known as Caldwell Valley from Walton Global in May 2025; coverage of that purchase placed it northwest of Lockhart and described plans for more than 2 gigawatts. No end customer for any Tract site in Texas appears in a public record found.
Website
tract.com

Legal entities named in the records: Medina County Power NR I, LLC; TXLCO Bexar County LLC; TXLCO Bexar County Two LLC; TXLCO San Antonio LLC; Tract Capital Management, LP. Search for these names, not only the company name, in agendas and appraisal records.

3 documented projects

On the record

Lawsuits, violations, fines and disputes reported about this company, each with its source. An allegation is described as one; it is not a finding.

  1. Texas: Medina County Power NR I, LLC filed a complaint at the Public Utility Commission (Docket 60356) appealing ERCOT's decision to classify its 500 MW Castroville-area project as studied load rather than base load. The commission paused the case in October 2026 while it considered related complaints. Source
  2. Hanover County, Virginia: the Board of Supervisors voted 4-3 to deny rezoning of nearly 430 acres for Tract's 900 MW Mountain Road Technology Park. Supervisors who voted no cited water use. Tract had offered $15 million for water infrastructure and a further $6 million payment. The article carries no Tract statement. Source
  3. Mooresville, North Carolina: Tract's representative withdrew the rezoning request for a proposed $30 billion data center on about 400 acres owned by Teresa Earnhardt, after residents opposed it over water and electricity use; about 200 people attended an August 4 meeting. A Tract spokesperson had earlier told The Charlotte Observer the company was "both disappointed and surprised" by the mayor's withdrawal of support. Source
  4. Farmington, Minnesota: residents and the Coalition for Responsible Data Center Development sued the City of Farmington over its rezoning for Tract's roughly 340-acre Farmington Technology Park, arguing the city needed Castle Rock Township's consent. The Pioneer Press reported the filing paused negotiations between the city and Tract. Tract declined to comment on the litigation but called a statement in the complaint "untrue, not based on any evidence" and said the city held a full, open and fair hearing. MPR News reported on 2024-12-16 that the suit was filed on November 29 in Dakota County District Court; the outcome was not checked. Source
  5. Maricopa County, Arizona: the Arizona Republic reported that the cities of Buckeye and Goodyear objected to Tract's request to rezone about 1,000 acres for two data center campuses, the larger of which was valued at roughly $12.8 billion to $14 billion, citing conflict with residential land-use plans, building height, noise and fire service. Tract responded that the objections concerned location, that the project would not need municipal water or sewer, and it cut the maximum building height from 110 to 60 feet. Source
  6. Maricopa County, Arizona (spring 2024): Tract's rezoning request for the roughly 1,000-acre Buckeye-area project was withdrawn after staff of Goodyear and Buckeye objected that it was incompatible with the land uses designated for the site, according to ABC15. The page is undated; the business-journal coverage it links is from March and April 2024. Source

Sources on the company

DateSourceFromLink
2026-09-30PUC Docket 60356: complaint and appeal of Medina County Power NR I, LLC
Cited from this site's Medina Technology Park record, which has the full docket history.
Public Utility Commission of TexasOpen
2026-05-28Hanover supervisors reject data center project on Mountain Road
4-3 denial; project terms; more than 30 speakers against and eight in support.
Richmond BizSenseOpen
2025-08-13Dale Earnhardt's widow backs off data center plan in Mooresville, North Carolina
Withdrawal of the rezoning request; headline paraphrased from the URL.
NBC NewsOpen
2025-05-07Walton Global Completes 1,515-Acre Sale in Caldwell County, Texas for Data Centers
Buyer named as Tract Management Company; two parcels of 1,088.37 and 426.85 acres. No capacity figure and no Tract statement.
Walton GlobalOpen
2025-01-09'We were completely ignored': Farmington residents sue the city in attempt to stop $5B data center park
Up to 12 buildings on about 340 acres; lawsuit against the city, not against Tract; Tract's statement.
Pioneer Press (republished by Yahoo News)Open
2024-12-16Farmington residents sue city over proposed data center
Says the Coalition for Responsible Data Center Development filed suit against the City of Farmington on November 29 in Dakota County District Court. No case number and no Tract statement.
MPR NewsOpen
2024-05-02Tract drops $14B plan to build data centers outside Phoenix
Refused automated access; the withdrawal is taken from the search excerpt.
The Real DealOpen
2024-03-28$14B data hub proposed near Buckeye. Here's why locals oppose it
Two campuses of 529 and 435 acres; objections from Buckeye and Goodyear planners; Tract's response.
The Arizona Republic (republished by Yahoo News)Open
Tract (portfolio page)
Lists Tract, Denver, as a digital infrastructure portfolio company that develops data center land. No date or stake given.
Columbia CapitalOpen
Berkshire Partners invests in Tract
Deal-tracker entry. Seen in search results; not opened.
MergrOpen
Building for the long term: Grant van Rooyen's Tract masterplan
Profile of the company and its founder. Seen in search results; not opened.
Data Center DynamicsOpen
Tract: Projects
The company's own list of sites. Cited from this site's I-35 Technology Park record.
TractOpen
Colorado Developer Plans Data Center on 1,515 Central Texas Acres
Source of the Lockhart location and the 2 gigawatt figure, from the search excerpt; not opened.
Industry Insider TexasOpen
Bexar CAD property 188191
A Lytle-area parcel owned by TXLCO Bexar County LLC, care of Tract Management Company LP in Denver: the link between the TXLCO name and Tract. Cited from this site's Applewhite record.
Bexar Appraisal DistrictOpen
Proposed data center in Farmington sparks resident pushback
Seen in search results; the site returned an error when opened.
Minnesota Star TribuneOpen
$14 billion West Valley data center project request withdrawn after cities push back
Undated page: Tract's rezoning request for about 1,000 acres in Buckeye's planning area was withdrawn after Goodyear and Buckeye staff objected. Does not give the number of applications or the withdrawal date. Title taken from the URL.
ABC15 ArizonaOpen