Approved · not yet builtTract · Record updated 2026-11-26
Draft record. This page has not yet been checked line by line against the source documents. Treat it as a lead, not a citation.
A 344.5-acre data center and business park site on the Bexar County side of Lytle, developed by Denver-based Tract. Lytle approved a development agreement and a utility service agreement; no tax abatement has been requested on the record.
Where this stands and what you can do
Local approvals are on record, but construction has not been reported. Terms already signed are hard to reopen. What is still open is anything not yet voted on: later phases, tax abatements, utility and road agreements, and state permits.
Find out what is still to be decided. Ask the city or county which approvals remain: annexation, a tax abatement, utility service, plats, road agreements. Each one is a vote where terms can be added.
A letter you can copy: ask for conditions before a vote
Send to: Mayor and council members. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: I-35 Technology Park - conditions before any vote
Dear Mayor and Council Members,
I live in [neighborhood / street] and I am writing about I-35 Technology Park (Tract).
I am not asking you to turn away investment. I am asking that no annexation, zoning change, utility agreement or tax abatement for this project be approved until the following are written into the ordinance or the agreement itself:
1. Water: a cap on annual water use, stated in acre-feet, with a yearly public report of actual use.
2. Noise: a limit measured at the property line, and set hours for testing backup generators.
3. Distance: a minimum setback and a buffer between the buildings, the generators and the nearest homes.
4. Power: disclosure of any on-site power plant or generators, and the air permits they will need.
5. Money: any tax abatement tied to a minimum investment, a jobs and wage floor, and a clawback if those are missed.
6. Transparency: the draft agreement posted publicly at least [14] days before the vote.
Please tell me which of these the current draft includes, and when the public will be able to read it.
Thank you,
[Name]
[Address]
[Phone or email]
Speak or write on any tax abatement not yet granted. If no abatement has been approved, it can still be denied or conditioned.
Send to: The body considering the abatement (city council or commissioners court). Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Tax abatement for I-35 Technology Park
Dear [Mayor and Council Members / Judge and Commissioners],
I am writing about the tax abatement requested for I-35 Technology Park (Tract).
A tax abatement is your decision to make; state law does not require one. Before you vote, I ask that you:
1. State publicly the percentage, the number of years, and the dollar value of the taxes that would be forgiven.
2. Compare the request with what other Texas cities and counties have granted for similar projects.
3. Require a minimum investment, a minimum number of full-time jobs at a stated wage, and repayment if those terms are not met.
4. Require an annual compliance report, posted publicly.
5. Explain what Lytle and Bexar County receive in return, and when.
If these terms cannot be met, I ask that you vote no.
Thank you,
[Name]
[Address]
Comment on state permits. Air authorizations for generators and on-site power are often filed after local approval.
A letter you can copy: write to your state senator and representative
Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.
Subject: Data center siting and reporting standards - Bexar County
Dear [Senator / Representative] [Name],
I am your constituent in Bexar County, where I-35 Technology Park (Tract) is [proposed / being built / operating] near homes.
I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
2. Require data centers above a set size to report their water and electricity use each year, publicly.
3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
Please tell me your position on these, and whether a bill addressing them is filed or planned.
Thank you,
[Name]
[Address - so your office can confirm I am a constituent]
TXLCO Bexar County LLC; TXLCO Bexar County Two LLC
Also known as
Master Planned Business Park and Integrated Datacenter
Location
South I-35 and Luckey Road
Jurisdiction
City of Lytle extraterritorial jurisdiction; annexation had not occurred as of 2026-10-24. The three Bexar CAD parcels found total about 321 acres; the development agreement was also recorded in Atascosa County, so part of the 344.5 acres may lie there.
Site
344.5 acres
Water
The utility service agreement dedicates 179.45 acre-feet of water rights to the city for 538 living unit equivalents (Resolution 26-01).
PUC Docket 60395: application of San Antonio Water System and City of Lytle for approval of a service area contract and to amend certificates of convenience and necessity in Bexar County
Docket index; look up control number 60395. The filings themselves have not been obtained.
Ordinance 26-01 extended the ETJ to the 344.5 acres and Resolution 26-01 approved a utility service agreement dedicating 179.45 acre-feet of water rights (both 4-0).
Resolution 25-52 approved a professional services agreement with TXLCO Bexar County LLC: an escrow so the developer pays the city's review costs. Staff called it a first step that approves no development (4-0).
Lytle City Council. Resolution 26-20 approved a service area agreement with SAWS to amend the two utilities' CCN boundaries (5-0).
Lytle City Council. Staff reported the development agreement fully executed and recorded in Bexar and Atascosa counties, with annexation to be looked at next.
Lytle City Council. Ordinance 26-01 extended the ETJ to the 344.5 acres and Resolution 26-01 approved a utility service agreement dedicating 179.45 acre-feet of water rights (both 4-0).
Lytle City Council. Tract presented the project. Resolution 25-57 approved a development agreement for about 344.5 acres, subject to ETJ expansion (5-0). Source
Lytle City Council. Resolution 25-52 approved a professional services agreement with TXLCO Bexar County LLC: an escrow so the developer pays the city's review costs. Staff called it a first step that approves no development (4-0).
See an error or have a document that belongs here? Tell us.