Bexar County / San Antonio /

Sentry Gateway Data Center

Operating · oversight onlyMicrosoft · Record updated 2026-11-27

Draft record. This page has not yet been checked line by line against the source documents. Treat it as a lead, not a citation.

A data center on a 28-acre lot owned by COPT San Antonio II, L.P., which state construction filings call EX West Green Data Center and TCEQ registers as Sentry Gateway Data Center with Microsoft Corporation as owner and operator. The site appears to be in operation: the appraisal district lists data center modules built 2019-2022, the state construction filings for both phases are closed, and TCEQ lists Microsoft as owner and operator with active air and tank registrations (air registration last revised June 2025). Microsoft also owns two adjoining lots (properties 1142335 and 1177240); the appraisal district dropped the improvement value on one of them from $17.5 million in 2025 to $0 in 2026, and neither shows a building in the 2026 appraisal records.

Where this stands and what you can do

The site is built and running. The options now are oversight: reporting problems, asking that the terms of its agreements be enforced, and weighing in when it asks to expand or renew a permit.

  1. Report noise, odor or smoke. Generator testing and on-site power are regulated by the state environmental agency. Complaints are logged and investigated.

    Contact: TCEQ: comment on a pending permit · TCEQ: environmental complaint

  2. Ask how the agreements are being enforced. If the site has a tax abatement or a utility agreement, ask for the annual compliance reports.

    Contact: San Antonio City Council · how to speak or comment

    A letter you can copy: ask how the agreements are being enforced

    Send to: City administrator or county judge, with a copy to your council member or commissioner. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Sentry Gateway Data Center - compliance with its agreements
    
    Dear [Name],
    
    I live near Sentry Gateway Data Center (Microsoft). The project has agreements with [the city / the county] that carry conditions. I would like to know how they are being checked. Please tell me:
    
    1. Which agreements are in force (tax abatement, development agreement, utility service, road use), and where the signed copies can be read.
    2. What the company must report each year, and whether those reports have been received.
    3. Who on staff is responsible for checking compliance, and what happens if a term is missed.
    4. How a resident should report a problem at the site (noise, dust, traffic, water), and to whom.
    
    If this is easier to answer as a public information request, please treat it as one under Government Code chapter 552.
    
    Thank you,
    [Name]
    [Address]
  3. Watch for expansions. New buildings, more generators and more water each need new permits or votes.

    Contact: Bexar County Commissioners Court

    A letter you can copy: write to the commissioners court

    Send to: County judge and commissioners. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center development in Bexar County - Sentry Gateway Data Center
    
    Dear Judge and Commissioners,
    
    I live in Bexar County near Sentry Gateway Data Center (Microsoft).
    
    I understand the county's power over land use outside city limits is limited. I am asking you to use the authority you do have:
    
    1. Grant no tax abatement or other incentive without a public hearing, published terms, and a clawback.
    2. Use the court's control over county roads to make sure the builder, not county taxpayers, pays for damage from construction traffic.
    3. Apply the county's subdivision, drainage and fire code rules in full, and say publicly which apply to this site.
    4. Post every agreement with a data center developer on the county website.
    5. Ask our state legislators for the authority counties need to set reasonable standards for projects of this size.
    
    Please let me know when the court will next take up an item involving this project.
    
    Thank you,
    [Name]
    [Address]
  4. Ask for the documents. Water use, permits and agreements are public records, though some utilities resist releasing them.

    Contact: How to file a public information request

  5. Ask the state for reporting rules. Whether a data center must disclose its water and power use is a question for the Legislature.

    Contact: Who Represents Me (Texas Legislature) · Office of the Texas Governor

    A letter you can copy: write to your state senator and representative

    Send to: Your Texas state senator and state representative. Fill in the brackets, cut what does not apply, and say it in your own words where you can. A short letter from a neighbor carries more weight than a form.

    Subject: Data center siting and reporting standards - Bexar County
    
    Dear [Senator / Representative] [Name],
    
    I am your constituent in Bexar County, where Sentry Gateway Data Center (Microsoft) is [proposed / being built / operating] near homes.
    
    I support data centers being built in Texas. My concern is where and how fast. Outside city limits, counties have almost no say, and neighbors learn the terms after the vote. I ask that you support legislation that would:
    
    1. Give counties authority to set reasonable siting standards for large data centers: setbacks from homes and schools, noise limits, and limits on on-site power generation near neighborhoods.
    2. Require data centers above a set size to report their water and electricity use each year, publicly.
    3. Require that tax abatement and development agreements with data centers be posted before the vote, not after.
    4. Require air permits and pollution controls to be in place before on-site turbines and generators run.
    
    Please tell me your position on these, and whether a bill addressing them is filed or planned.
    
    Thank you,
    [Name]
    [Address - so your office can confirm I am a constituent]

This is general information about how local and state decisions get made, not legal advice.Who decides what, and every contact and letter in one place.

Legal entities
Microsoft Corporation; COPT San Antonio II, L.P.
Also known as
EX West Green Data Center; 1050 Democracy Blvd; Sentry Gateway Crossing; 7600 W Military Dr
Location
1050 Democracy Boulevard, off West Military Drive south of Potranco Road; the appraisal district carries the data center lot as 7600 W Military Dr
Jurisdiction
Inside San Antonio city limits (zoned C-3 and C-2 on the appraisal records).
Site
28.046 acres
Investment
State construction filings (TDLR) by the owner, COPT San Antonio II, L.P.: $22.5 million (2018), $279,988,945 for phase 2 (2021), $7.4 million (2023) and $15 million (2024).

Documents and sources

20 items: Government records (16) · Appraisal district records (3) · News and company statements (1)

Government records

Ordinances, resolutions, agreements, notices, permits and filings.

DateDocumentFromLink
2025-06-23TCEQ air permit project 393847, registration 156500 (Sentry Gateway Data Center)
PBR Existing Registration. Action: revision (PBR); received 06/02/2025; permit status issued; completed 06/23/2025. Applicant: Microsoft Corporation.
Texas Commission on Environmental QualityOpen
2024-11-01TDLR TABS2025004677, Admin 2 Building
1050 Democracy Blvd. $750,000; a 1,200 sq ft pre-manufactured modular office building on the existing jobsite; 12/1/2024 to 6/1/2025. Owner Microsoft Corporation. Status: inspection complete.
Texas Department of Licensing and RegulationOpen
2024-08-21TDLR TABS2024025975, EX West Green Data Center (Ex West New MMR's)
1050 Democracy. $15,000,000; two more 800 sq ft meet-me room buildings; 12/16/2024 to 11/14/2025.
Texas Department of Licensing and RegulationOpen
2023-09-13TDLR TABS2024000855, EX West Green Data Center (meet-me rooms)
1050 Democracy. $7,400,000; two 800 sq ft meet-me room buildings; 10/2/2023 to 3/29/2024.
Texas Department of Licensing and RegulationOpen
2022-03-11TCEQ petroleum storage tank registration 90355: investigations
One investigation listed: 03/11/2022, compliance investigation file review. Microsoft Corporation has been owner and operator since 12/14/2018. No violations are shown.
Texas Commission on Environmental QualityOpen
2021-08-17TCEQ air permit project 331820, registration 156500 (Sentry Gateway Data Center)
PBR Existing Registration. Action: revision (PBR); received 07/30/2021; permit status issued; completed 08/17/2021. Applicant: Microsoft Corporation.
Texas Commission on Environmental QualityOpen
2021-02-08TDLR TABS2021008977, EX West Green Data Center Phase 2
1050 Democracy. $279,988,945; 88,980 sq ft; phase 2 on a 28.05-acre greenfield site: a one-story operations office, storage containers, modular data center containers with electrical and mechanical equipment, yards and covered walkways; 1/31/2021 to 3/27/2023. Owner COPT San Antonio II, LP.
Texas Department of Licensing and RegulationOpen
2019-05-03TCEQ air permit project 299946, registration 156500 (Sentry Gateway Data Center)
PBR New Registration. Action: initial registration (PBR); received 04/14/2019; permit status issued; completed 05/03/2019. Applicant: Microsoft Corporation.
Texas Commission on Environmental QualityOpen
2018-08-22Planning Commission file 18-4660: rescission of plat 120413 extension, Sentry Gateway, Building 300 Subdivision
Request by COPT San Antonio II, L.P. to rescind the extension approved 2016-06-08; staff recommended approval. From the city's Legistar matter index; the agenda and minutes were not obtained.
City of San Antonio Planning CommissionNot yet archived. Have it?
2018-07-05TDLR EABPRJB8820869, EX West Green Data Center
1050 Democracy. $22,500,000; new construction; 8/1/2018 to 4/1/2019. Owner COPT San Antonio II L.P.; design firm Page. Status: project closed.
Texas Department of Licensing and RegulationOpen
2016-06-08Planning Commission file 16-3456: site improvement time extension, Sentry Gateway, Bldg 300 Subdivision (plat 120413)
Request by COPT San Antonio II, LP for a three-year extension; staff recommended approval. From the city's Legistar matter index; the agenda and minutes were not obtained.
City of San Antonio Planning CommissionNot yet archived. Have it?
TCEQ RN110636149, Sentry Gateway Data Center, 1050 Democracy Blvd: air registration 156500 and tank registration 90355
Owner and operator Microsoft Corporation. Primary business: data center operations. Air new source registration 156500 (active); petroleum storage tank registration 90355 (active). If the link errors, search the RN at www15.tceq.texas.gov/crpub.
Texas Commission on Environmental QualityOpen
Qualifying data center registry
Checked 2026-11-27: no row for Sentry Gateway, EX West Green or COPT San Antonio II.
Texas ComptrollerOpen
Chapter 312 abatement agreement registry (statewide data file)
Checked 2026-11-27: no Microsoft or COPT San Antonio II entry among the 169 Bexar County rows.
Texas ComptrollerOpen
Demolition or building permits for 1101 Sentry Gateway
Not obtained. The appraisal district removed all improvement value from property 1142335 for 2026; no permit explaining the change was located.
City of San Antonio Development Services DepartmentNot yet archived. Have it?
EX West Green Data Center
Tracker page attributing the development to Corporate Office Properties Trust.
CleanviewOpen

Appraisal district records

The county appraisal district page for each parcel: owner, value, deed history.

DateDocumentFromLink
Bexar CAD property 1300579
7600 W Military Dr. NCB 16955 (Sentry Gateway Crossing), Block 2, Lot 5; 28.046 acres; owner COPT San Antonio II LP, Columbia, Maryland (the county parcel layer lists it care of Microsoft Corp); zoning C-3. Main building 118,393 sq ft, year built 2019, plus six smaller improvements. Market value $56,500,000 in 2025 and 2026 (improvements $47,679,440).
Bexar Appraisal DistrictOpen
Bexar CAD property 1142335
1101 Sentry Gateway. NCB 16955 (Military Drive Business Park, Unit 1), Block 2, Lot 2; 4.434 acres; owner Microsoft Corporation; zoning C-2. Improvement value $14,412,540 (2023), $16,162,540 (2024), $17,493,220 (2025) and $0 (2026); the 2026 record lists no improvements and a total value of $2,006,780.
Bexar Appraisal DistrictOpen
Bexar CAD property 1177240
W Military Dr. NCB 16955, Block 2, Lot 4 (Sentry Gateway Bldg 200); 3.988 acres; owner Microsoft Corporation; zoning C-2. Improvement value $100 since 2024; total value $1,500,000 in 2026.
Bexar Appraisal DistrictOpen

News and company statements

Reporting and press releases. These are not public records; they are context and leads.

DateDocumentFromLink
COPT to build meet-me rooms at Texas data center for $7.4m
Link from search results; not opened.
Data Center DynamicsRead

Timeline

  1. Texas Commission on Environmental Quality. Air registration 156500 revised again; the application was received 2025-06-02.
  2. Texas Commission on Environmental Quality. Air registration 156500 revised.
  3. Texas Department of Licensing and Regulation. Phase 2 registered: modular data center containers and support equipment on the 28.05-acre site, $279,988,945, 1/31/2021 to 3/27/2023.
  4. Texas Commission on Environmental Quality. Initial permit by rule registration 156500 issued to Microsoft for Sentry Gateway Data Center.
  5. Texas Commission on Environmental Quality. Microsoft Corporation became registered owner and operator of the petroleum storage tanks at the site.
  6. Texas Department of Licensing and Regulation. EX West Green Data Center registered at 1050 Democracy by COPT San Antonio II L.P.: $22.5 million, 8/1/2018 to 4/1/2019.