| 2026-11-02 | TCEQ air quality complaint 467890, Vantage TX 11 One complainant; received 11/02/2026, closed 11/19/2026; program air quality. TCEQ's San Antonio regional office describes it as a complaint concerning permit compliance, assigned to an investigator; investigation details are withheld until the report is approved. It is the only complaint listed for the site in Central Registry. | Texas Commission on Environmental Quality | Open |
| 2026-10-09 | TCEQ air permit project 416475, registration 177637 (VoltaGrid SAT-1 gas engines) Standard Permit For Existing Registration. Action: revision (STDPMT); received 10/09/2026; action pending as of 2026-11-27 (the existing registration is effective). Applicant: Voltagrid LLC. | Texas Commission on Environmental Quality | Open |
| 2026-09-21 | Public Citizen et al. v. Vantage Data Centers Management Company, LLC et al., No. 5:26-cv-06032 (W.D. Tex.) Clean Air Act citizen suit filed in San Antonio federal court against Vantage and VoltaGrid. Law360 names Public Citizen and the Sierra Club as plaintiffs, with the Environmental Integrity Project as their counsel; the San Antonio Current and News 4 describe all three groups as filing. The complaint and docket were not obtained; the case number is as reported by Law360 and MLex, the filing date as reported by the San Antonio Current and Law360. News 4 reported the plaintiffs seek an order stopping construction and operation until major-source permits are obtained. | U.S. District Court, Western District of Texas | Not yet archived. Have it? |
| 2026-08-11 | Cancellation of Notice and Comment Hearing, Vantage Data Centers TX11, LLC, Draft Permit No. O4791 Chief Clerk's letter: the hearing set for 2026-08-17 is cancelled and will be rescheduled, with notice by mail. | Texas Commission on Environmental Quality | Open |
| 2026-07-24 | TCEQ air permit project 411374, registration 177637 (VoltaGrid SAT-1 gas engines) Standard Permit For Existing Registration. Action: revision (STDPMT); received 06/24/2026; permit status issued; completed 07/24/2026. Applicant: Voltagrid LLC. | Texas Commission on Environmental Quality | Open |
| 2026-07-22 | Notice of intent to sue under the Clean Air Act, Vantage Data Centers and VoltaGrid Sent on behalf of Sierra Club and Public Citizen to Vantage Data Centers TX11, LLC, Vantage Data Centers TX21, LLC, Vantage Data Centers Management Company, LLC and VoltaGrid LLC, and addressed to the EPA Administrator and TCEQ, with copies to EPA Region 6, the companies' registered agents and the governor. Alleges five claims: that each campus (14270 Omicron Drive, as the notice gives the address, and 5207 Rogers Road) is a major source built without nonattainment or PSD pre-construction permits, and that the Rogers Road diesel generators ran as primary power in 2025. States 423 MW of gas generation and 454 MW of diesel backup across both campuses; lists the permit numbers, engine counts and permitted tons per year. Starts a 60-day waiting period. | Sierra Club and Public Citizen (through the Environmental Integrity Project, their counsel) | Open |
| 2026-02-09 | TDLR TABS2026012091, TX12 TFO 17420 Omicron Dr. $448,000,000; 174,812 sq ft; tenant build-out of 96 MW of data modules; start 8/19/2026, completion 3/30/2028. | Texas Department of Licensing and Regulation | Open |
| 2026-02-04 | TDLR TABS2026011691, TX11 OMC 14720 Omicron Dr. $900,000; 6,345 sq ft office renovation; start 6/2/2026, completion 10/9/2026. | Texas Department of Licensing and Regulation | Open |
| 2025-12-18 | TDLR TABS2026008433, TX11 OPEL Fit-Up 14720 Omicron Dr. $95,000,000; 117,044 sq ft; 32 MW tenant build-out; start 1/7/2026, completion 6/12/2026. Owner Vantage Data Centers TX11. Status: inspection complete. | Texas Department of Licensing and Regulation | Open |
| 2025-09-18 | TDLR TABS2026001234, Vantage Data Center (TX12) 17420 Omicron Dr. $276,878,327; 432,800 sq ft; two stories; up to 96 MW of critical IT capacity; start 10/14/2025, completion 8/31/2027. Owner Vantage Data Centers TX1 LLC. | Texas Department of Licensing and Regulation | Open |
| 2025-05-09 | TCEQ air permit project 391320, registration 175523 (Vantage TX11 diesel generators) PBR Existing Registration. Action: revision (PBR); received 04/07/2025; permit status issued; completed 05/09/2025. Applicant: Vantage Data Centers Tx11, LLC. | Texas Commission on Environmental Quality | Open |
| 2024-10-10 | TCEQ air permit project 380453, registration 177637 (VoltaGrid SAT-1 gas engines) Standard Permit New Registration. Action: initial registration (STDPMT); received 09/20/2024; permit status issued; completed 10/10/2024. Applicant: Voltagrid LLC. | Texas Commission on Environmental Quality | Open |
| 2024-10-01 | TDLR TABS2025002159, TX11-SAT26 14720 Omicron Dr. $50,000,000; 114,912 sq ft; customer office and 32 MW tenant build-out; start 11/11/2024, completion 8/12/2025. | Texas Department of Licensing and Regulation | Open |
| 2024-02-29 | TCEQ air permit project 370963, registration 175523 (Vantage TX11 diesel generators) PBR New Registration. Action: initial registration (PBR); received 02/29/2024; permit status issued; completed 02/29/2024. Applicant: Vantage Data Centers Tx11, LLC. | Texas Commission on Environmental Quality | Open |
| 2023-12-15 | TDLR TABS2024007561, Data Center Building TX11 14720 Omicron Dr. $95,823,731; 242,667 sq ft; two stories, four 8 MW data halls, 32 MW total; start 12/15/2023, completion 9/1/2026. Owner Vantage Data Centers TX1 LLC. Status: inspection complete. | Texas Department of Licensing and Regulation | Open |
| TCEQ RN111852240, Vantage TX 11, 14720 Omicron Dr: air registration 175523, federal operating permit O4791 (pending), tank registration, stormwater Owner and operator Vantage Data Centers TX11, LLC; The Whiting-Turner Contracting Company is listed as an operator. Air new source registration 175523 (active), air operating permit 4791 (pending), emissions inventory account BGA039M (active), petroleum storage tank registration 94526 (active), construction stormwater permits TXR1535PD (active) and TXR1511PF (cancelled). If the link errors, search the RN at www15.tceq.texas.gov/crpub. | Texas Commission on Environmental Quality | Open |
| TCEQ federal operating permit O4791, commissioners' action item 145918 (public notice history) Lists the notice steps for the pending permit: public hearing approved by the executive director 05/15/2026; notice of public hearing received 06/17/2026 and mailed 06/26/2026; notice of application published 07/10/2026; notice of public meeting cancelled 08/11/2026. No TCEQ or SOAH docket number is shown. | Texas Commission on Environmental Quality | Open |
| Cancellation of Notice & Comment Hearing: Vantage Data Centers TX11, LLC, O4791 (hearing calendar page) Says the hearing will be rescheduled for a later date. | Texas Commission on Environmental Quality | Open |
| TCEQ RN112050760, VoltaGrid SAT-1 EGU, 14720 Omicron Dr #2: standard permit registration 177637 Owner and operator VoltaGrid LLC. Air new source registration 177637 (active); emissions inventory account BGA034H (active). The notice of intent to sue says this standard permit for electric generating units was obtained 2024-10-10 and covers 80 Jenbacher J620 natural gas engines of 3,310 kWe each, with permitted limits of 49.97 tons per year NOx, 215.14 CO, 24.29 VOC and 31.54 formaldehyde. If the link errors, search the RN at www15.tceq.texas.gov/crpub. | Texas Commission on Environmental Quality | Open |
| TCEQ Investigation Report No. 2122581, VoltaGrid Omicron Drive plant Not obtained. Cited in the notice of intent to sue: as of 2026-01-12 VoltaGrid had built 20 J620 engines, ten of them operational. The notice links a copy in TCEQ's records portal. | Texas Commission on Environmental Quality | Not yet archived. Have it? |
| TCEQ air new source registration 177637 (VoltaGrid SAT-1 EGU): investigations Three compliance investigations listed, dated 01/20/2026, 01/21/2026 and 01/22/2026. No result is shown. If the link errors, search the RN at www15.tceq.texas.gov/crpub. | Texas Commission on Environmental Quality | Open |
| TCEQ RN111939062, Vantage Data Center TX-A (CPS Energy): construction stormwater permit TXR1544QG Cancelled. Operator: City Public Service Energy. Northwest of Omicron Dr and Theta Dr. If the link errors, search the RN at www15.tceq.texas.gov/crpub. | Texas Commission on Environmental Quality | Open |
| Plat, TX11 subdivision (CB 4349A, Block 130, Lots 1-3) Not obtained. The plat name comes from the legal description on the appraisal records. | City of San Antonio Planning Commission / Bexar County | Not yet archived. Have it? |
| Vantage San Antonio TX1 campus Industry tracker page. | Baxtel | Open |
| Vantage TX11 | Baxtel | Open |
| Vantage TX11 | Cleanview | Open |
| Bexar County projects Tracker summary of the TDLR filings for TX11 and TX12. | Texas Data Center Watch | Open |
| Qualifying data center registry (large data center projects) Row "TX11-12 Data Center": effective 11/05/2025; owners Vantage Data Centers TX11, LLC and Vantage Data Centers TX12, LLC; occupant Oracle America Cloud Services, LLC; operators Vantage Data Centers Management Company, LLC and Oracle America, Inc. An earlier row on the qualifying data center list, "TX11 Data Center", effective 03/06/2024 with occupant Microsoft Corporation, carries an end date of 11/4/2025. The registry gives a state sales tax exemption; it lists no address. | Texas Comptroller | Open |
| Chapter 312 abatement agreement registry (statewide data file) Checked 2026-11-27: no Vantage entry among the 169 Bexar County rows. | Texas Comptroller | Open |
| City of San Antonio council, zoning and incentive records Not searched for 2022 onward: the Legistar title index used ends in 2021. News coverage describes no city incentive or rezoning. The plats named in the appraisal records were not located in Planning Commission agendas. | City of San Antonio | Not yet archived. Have it? |
| CPS Energy and SAWS board items None found naming Vantage. CPS Energy holds cancelled construction stormwater permits at both campuses (TCEQ). | CPS Energy / San Antonio Water System | Not yet archived. Have it? |