Companies /

Vantage Data Centers

Draft record. This page has not yet been checked line by line against its sources. Treat it as a lead, not a citation.

Vantage Data Centers builds data center campuses and leases them to large technology companies. It has two campuses under construction in San Antonio, each powered by an on-site natural gas plant run by VoltaGrid and registered with the state with Oracle as occupant, and it is building the Frontier campus in Shackelford County. Environmental groups sued Vantage and VoltaGrid under the Clean Air Act in September 2026 over the San Antonio air permits.

Also known as
Vantage; Vantage Data Centers Management Company, LLC; Vantage Data Centers TX1 LLC; Vantage Data Centers TX2 LLC; Vantage Data Centers TX11, LLC; Vantage Data Centers TX12, LLC; Vantage Data Centers TX21, LLC; Vantage Data Centers TX22, LLC; Vantage Data Centers TX301, LLC through TX310, LLC; Vantage Data Centers TX41, LLC; Vantage Data Centers TX51, LLC
Type
Hyperscale data center developer and landlord
Headquarters
Denver, Colorado
Ownership
Privately held. Its 2024 equity raises of $6.4 billion and $9.2 billion were led by investment vehicles managed by DigitalBridge Group and Silver Lake, according to the companies' announcements. In Texas it holds each building in a separate LLC (TX11, TX12, TX21, TX22, TX301 to TX310) with Vantage Data Centers Management Company, LLC as operator.
Elsewhere in Texas
Bexar County: the TX1 campus on Omicron Drive at Texas Research Park (TX11, TX12) and the TX2 campus on Rogers Road in Westover Hills (TX21, TX22). Shackelford County: the Frontier campus near Hamby, announced 2025-08-19 as more than $25 billion, 1.4 GW, ten buildings and 3.7 million square feet on about 1,200 acres; trade and advocacy sources describe it as a site for Oracle and OpenAI with on-site gas generation. The Texas Comptroller's registry lists ten rows, "TX 301 Data Center" through "TX 310 Data Center" (effective 2025-10-08, occupant Oracle America Cloud Services LLC), which match the ten-building Frontier plan although the registry gives no address, and two further rows, "TX4" and "TX5" (effective 2026-11-16, Vantage Data Centers TX41, LLC and TX51, LLC), whose location was not established. Incentives on record: state sales tax exemption registrations for all of these; and in Shackelford County, the Commissioners Court unanimously created Reinvestment Zone 2025-1 and accepted Vantage's abatement application in July 2025, with a reported 10-year arrangement of $10 million a year paid to the county in place of property taxes (The Albany News). The signed Shackelford agreement was not obtained and does not appear in the Comptroller's Chapter 312 registry file. No local abatement was found for the San Antonio campuses.
Website
vantage-dc.com

Legal entities named in the records: Oracle America Cloud Services, LLC; Oracle America, Inc.; Vantage Data Centers Management Company, LLC; Vantage Data Centers TX1 LLC; Vantage Data Centers TX11, LLC; Vantage Data Centers TX12, LLC; Vantage Data Centers TX2 LLC; Vantage Data Centers TX21, LLC; Vantage Data Centers TX22, LLC; VoltaGrid LLC. Search for these names, not only the company name, in agendas and appraisal records.

2 documented projects

On the record

Lawsuits, violations, fines and disputes reported about this company, each with its source. An allegation is described as one; it is not a finding.

  1. San Antonio: a Clean Air Act citizen suit was filed against Vantage and VoltaGrid in federal court (No. 5:26-cv-06032, W.D. Tex., per this site's facility records), asking the court to halt construction and operation until major-source permits are obtained. The San Antonio Current describes the Environmental Integrity Project, Sierra Club and Public Citizen as filing it; the July notice of intent was sent for the Sierra Club and Public Citizen, with the Environmental Integrity Project as their counsel, and the complaint was not obtained. The San Antonio Current and News 4 San Antonio each reported that Vantage and VoltaGrid did not respond to requests for comment. No ruling was found. Source
  2. San Antonio: residents near the TX1 campus reported a natural gas odor. Vantage said it knew of no incident posing a risk, according to KSAT as summarized in this site's TX1 record. Source
  3. San Antonio: TCEQ cancelled the notice and comment hearing on draft federal operating permit O4791 for the TX1 campus that had been set for 2026-08-17, saying it would be rescheduled (TCEQ letter of 2026-08-11). Source
  4. San Antonio: the Sierra Club and Public Citizen, through their counsel at the Environmental Integrity Project, sent Vantage and VoltaGrid a notice of intent to sue under the Clean Air Act. The groups say the two campuses and their gas plants (423 MW by the groups' count, with 151 diesel backup generators) were built under four minor-source registrations when major-source permits were required, and estimate potential emissions of about 5,600 tons of nitrogen oxides a year. These are the groups' figures. Their release carries no company response. Source
  5. San Antonio: TCEQ held a notice and comment hearing on draft federal operating permit O4790 for the TX2 campus on Rogers Road. See this site's TX2 record for attendance and testimony. Source
  6. Wisconsin: the group Great Lakes Neighbors United said it had gone to court alleging the Port Washington Common Council negotiated the Vantage development agreement in improperly closed sessions. The city said it knew only of a complaint to the district attorney and that it had complied with open meetings law. Vantage is not a party to the complaint. Source
  7. Wisconsin: three members of a group opposing Vantage's $15 billion Port Washington campus, built for OpenAI and Oracle, were arrested and cited for disorderly conduct at a Common Council meeting, according to FOX6 and Wisconsin Public Radio. Opponents objected to the city's tax increment financing deal, the campus's expected 1.3 GW power draw and its water use, and began a recall effort against the mayor, which the city said in February 2026 was several hundred signatures short on its initial review. Source

Sources on the company

DateSourceFromLink
2026-09-22Environmental groups sue developers of two SA data centers over air pollution permits
Says Vantage and VoltaGrid did not respond; reports the Governor ordered TCEQ to stop issuing data center permits pending a state audit.
News 4 San AntonioOpen
2026-09-21Environmental groups sue over San Antonio data centers
Reports the federal suit and the relief sought; gives the gas plants as 405 MW. Says neither company could be reached.
San Antonio CurrentOpen
2026-09-18People report strong natural gas odor near far West Side data center
Described from this site's TX1 record; not re-read for this company record.
KSATOpen
2026-08-12Abbott says two San Antonio data centers will comply with new standards
Reports the Governor's announcement, the cancelled TCEQ hearing and the environmental groups' objections.
News 4 San AntonioOpen
2026-08-12Governor Abbott Announces Core Scientific, Vantage Data Centers And SB Energy Commit To Comply With His Data Center Standards
Lists the standards and the disclosures the PUC and ERCOT will audit. No statement from Vantage is included.
Office of the Texas GovernorOpen
2026-08-11Cancellation of Notice and Comment Hearing, Vantage Data Centers TX11, LLC, Draft Permit No. O4791
Letter cancelling the hearing set for 2026-08-17 and saying it will be rescheduled.
Texas Commission on Environmental QualityOpen
2026-07-22Notice of intent to sue under the Clean Air Act: Vantage Data Centers and VoltaGrid
The groups' allegations and permit history for both San Antonio campuses; summarized in detail in this site's TX1 and TX2 records.
Environmental Integrity Project, as counsel for the Sierra Club and Public CitizenOpen
2026-07-22Environmental groups take legal action against illegal data center and power plant projects in San Antonio
The groups' summary: 423 MW of gas generation, 151 diesel generators, four minor-source registrations issued in 2024 and 2025, and estimated potential emissions. An advocacy source; "illegal" is the groups' characterization.
Environmental Integrity ProjectOpen
2026-04-06Notice of hearing: Vantage Data Centers TX21, LLC, draft federal operating permit O4790
Hearing notice for the TX2 campus; described from this site's TX2 record.
Texas Commission on Environmental QualityOpen
2026-02-18Port Washington data center; lawsuit alleges open meetings violations
The group's allegations and the city's denial that any lawsuit had been filed.
FOX6 MilwaukeeOpen
2026-02-16Port Washington mayor recall falls short after data center dispute
The city said its initial review found the recall petition several hundred signatures short; the clerk's formal determination was still pending.
FOX6 MilwaukeeOpen
2025-12-18Data center deal puts Port Washington mayor on recall hot seat
Port Washington campus: $15 billion, 1.3 GW, tax increment financing, three arrests at a council meeting, recall petition. No Vantage statement.
Wisconsin Public Radio via Urban MilwaukeeOpen
2025-12-03Port Washington data center; 3 arrested after 'disturbance' at meeting
Three women arrested and cited for disorderly conduct at the Common Council meeting of 2025-12-02.
FOX6 MilwaukeeOpen
2025-08-19Vantage Data Centers Unveils Plans for "Frontier," a $25B Mega-campus in Texas to Meet Unprecedented AI Demand
The page refused an automated request; details here are from search-result excerpts of the release: 1,200 acres, 1.4 GW, ten data centers, 3.7 million square feet, more than 5,000 jobs across construction and operations, and a closed-loop cooling design the company says needs little water.
Vantage Data CentersOpen
2025-08-19Vantage Plans $25B, 10-Building Data Center Campus In Central Texas
Confirms the investment, capacity and square footage for the Shackelford County campus.
BisnowOpen
2025-07-311,200-acre data center in Shackelford County could boost local economy
County Judge John Viertel on the payment terms, fire training for volunteer departments and water supply questions. The dollar figures are garbled in the republished text.
KTAB/KRBC via Yahoo NewsOpen
2025-07-24Data center plans move forward in Shackelford County
Commissioners' unanimous approval of Reinvestment Zone 2025-1 and acceptance of the abatement application; payment and scholarship terms; site of about 1,200 acres at Highways 604 and 351.
The Albany NewsOpen
2024-06-13Vantage Data Centers Completes $9.2 Billion Equity Investment Led by DigitalBridge and Silver Lake
Seen in search results, not opened. Source for the lead investors.
Vantage Data CentersOpen
Qualifying data center and large data center project registries
State sales tax exemption registry. Vantage rows: "TX11 Data Center" DC536960 (2024-03-06, occupant Microsoft Corporation, ended 2025-11-04); "TX11-12 Data Center" LD783253 and "TX21-22 Data Center" LD521147 (2025-11-05, occupant Oracle America Cloud Services, LLC; operators Vantage Data Centers Management Company, LLC and Oracle America, Inc.); "TX 301" through "TX 310 Data Center" (2025-10-08, occupant Oracle America Cloud Services LLC); "TX4" LD307829 and "TX5" LD638080 (2026-11-16, owner, occupant and operator Vantage Data Centers TX41, LLC and TX51, LLC). The registry gives no addresses.
Texas Comptroller of Public AccountsOpen
Chapter 312 tax abatement registry (detail file)
Searched for Vantage and VoltaGrid; no rows, including for Shackelford County.
Texas Comptroller of Public AccountsOpen
Shackelford County tax abatement agreement with Vantage Data Centers (Reinvestment Zone 2025-1)
Not obtained. The Albany News reported on 2025-07-24 that commissioners accepted the application and would sign an agreement once Vantage closed on the land; whether and when it was signed was not established.
Shackelford CountyNot yet archived.
Vantage Data Centers and VoltaGrid establish partnership to deploy more than one gigawatt of power generation
Listed in this site's facility records; the page refused an automated request when checked for this record, so it was not re-read.
Vantage Data CentersOpen

Record updated 2026-11-27